Construction Plan for Mobile Toilets in Nyingchi
The construction plan for mobile toilets in Nyingchi can refer to the following key points and be adjusted for implementation based on the actual situation of local tourism toilet construction projects:

I. Project Overview and Design Positioning Mobile toilets are modular integrated facilities. The main body is assembled from prefabricated modules made of steel structures or composite panels, which are disassembled into components for transportation and quickly assembled on-site. In view of the characteristics of Nyingchi's tourist attractions, the following designs need to be emphasized:
- Functional Adaptation: Add deodorization devices and mother-and-child toilet stalls to meet the needs of tourists in high-altitude areas.
- Environmental Protection and Energy Efficiency: Equip with non-flush toilets and solar power supply systems to reduce dependence on municipal pipe networks.
- Wind and Earthquake Resistance: The main structure has a wind resistance rating of ≥8 to adapt to Nyingchi's windy climate.
- Waterproofing and Moisture Resistance: Adopt a sealed design that has passed waterproofing tests without leakage to cope with the local rainy season.
II. Construction Deployment
- Objectives and Principles:
- Four Compliance Standards: Quality (main structure wind resistance ≥8), safety (zero casualties), progress (delivery within 72 hours), and environmental protection (noise ≤60 decibels, 100% waste classification).
- Construction Sequence: Adhere to the principle of "underground before above-ground, main body before decoration" to avoid rework.
- Organizational Structure:
- A dedicated team of 5-8 people, including a project manager (overall coordination), a technical leader (drawing review), a construction team leader (with 3-4 installers), a safety officer (full-time patrol), and a logistics officer (material coordination).
- Site Preparation:
- On-site surveys should identify underground cables and water pipes. Use a total station to measure ground flatness with an error controlled within ±5mm.
III. Construction Arrangement
- Special Management Objectives:
- Project Duration: Clearly define installation nodes for each area, such as 24 hours for foundation construction and 48 hours for main body assembly.
- Quality: Full-time quality inspectors should have 100% on-site coverage, meeting national standards.
- Safety: No safety accidents, complying with the "Construction Safety Inspection Standards".
- Construction Preparation:
- Labor Organization: Electricians, welders, and other special trades should hold relevant certificates and receive training on construction techniques and safety regulations before entering the site.
- Technical Preparation: Drawing reviews should focus on design changes and construction difficulties, and use a total station for measurement and layout.
IV. Reference Project Information The tourism toilet renovation project in Gongbu'gyamda County, Nyingchi (project number gzfcg2026-35710) covers projects in Jieba Village, Linze Village, and other areas. Potential suppliers can obtain documents through the Tibet Public Resources Trading Platform, with a deadline of September 8, 2026. The construction plan can draw on its environmental protection requirements and modular design experience.