The installation of mobile toilets in Wuda can refer to the following general steps, which need to be flexibly adjusted according to on-site conditions:

I. Planning and Preparation Before Installation
Site Assessment and Location Selection
- Survey the overall layout and select a location on the edge of an area with heavy pedestrian traffic or near a passageway, avoiding the upwind side of activity areas to reduce odor impact.
- Ensure the ground is flat and solid. If the ground is soft (such as mud or sand), lay pads or wooden planks in advance to distribute the load.
- Be close to water supply points and sewage discharge interfaces, or plan a route for water trucks to ensure convenient subsequent connections.
Determine Requirements and Specifications
- Calculate the required number and type of toilets based on the number of users, the duration of the event, and the male-to-female ratio.
- Weigh the pros and cons of single-unit toilets (flexible but with limited service capacity) and large-scale units (fully functional but requiring more space) and choose a model suitable for the scenario.
Material and Personnel Preparation
- Prepare pads, drinking-water-grade hoses, sewage pipes, tools (wrenches, spirit levels, etc.), cleaning and disinfection supplies, and consumables.
- Arrange installation personnel with knowledge of water and electricity connections and safety operation specifications to ensure construction standards.
II. On-site Installation Steps
Site Leveling and Positioning
- Clear debris from the site and use measuring tools to determine the position of the toilet units, reserving queuing space (it is recommended to reserve 1-1.5 meters around each unit).
- If the ground is uneven, level it with pads or adjustable feet to prevent the toilet from tilting.
Unit Placement and Stabilization
- Use a forklift or trailer to move the toilet units to the designated positions and place them gently to avoid damage.
- Use a spirit level to check the levelness and make fine adjustments with adjustable feet or wedges to ensure stability without shaking.
System Connections
- Water Supply Connection: Connect one end of the hose to a reliable water source (such as municipal water supply or a water tank) and the other end to the toilet water inlet. Check if the water pressure meets the standard (usually ≥0.2MPa) and empty the air in the pipe to prevent air resistance.
- Sewage Discharge Connection: If it is a direct-discharge type, ensure that the sewage pipe is unobstructed and has a reasonable slope (it is recommended that the slope be ≥2%); if it is a fecal-storage type, reserve a cleaning port and seal it.
III. Detail Handling and Finalization
- Clean the inside and outside of the toilets and check if all bolts and nuts are tightened to prevent safety hazards caused by loosening.
- Test whether the water supply and sewage discharge systems are normal and check if functions such as flushing and lighting are intact.
- For daily maintenance, regularly clean and disinfect, check the tightness of the pipelines, and clean the fecal storage tank (if applicable) to extend the service life.
Precautions:
- Before installation, check if the sewage pipe is blocked and if the ground is level to avoid rework later.
- If toilet bowl installation is involved, determine the center line of the sewage pipe, pre-embed expansion screws, and properly seal the bottom (such as installing a sealing ring or applying glass glue) to prevent leakage.