Prefabricated Housing Contract Agreement
The prefabricated housing contract agreement should include key elements such as project overview, contracting method, project duration, cost and payment, quality inspection, responsibilities of both parties, liability for breach of contract, and other matters, as detailed below:

I. Project Overview The project name (e.g., 'XX Village Brick-and-Mortar Prefabricated Housing Project'), location (precise to district, town, village, and orientation), building area (filled in according to the design area, in square meters), and building structure (e.g., 'brick-and-mortar prefabricated structure, two stories') should be clearly specified. This section serves as the foundational information of the agreement and must align with the actual design.
II. Contracting Method There are two types:
- Labor and Materials Contract: Party B is responsible for purchasing all materials (such as red bricks, cement, and steel) and conducting the construction, while Party A provides the design drawings.
- Labor-Only Contract: Party A supplies the materials, and Party B only provides labor, technology, and tools. The choice should be made and clearly specified based on mutual negotiation between the two parties.
III. Project Duration The start date (e.g., 'XXXX/XX/XX') and completion date (which can be a specific date or the number of construction days) should be clearly defined. If construction is halted due to reasons attributable to Party A (such as material shortages or insufficient funding), the project duration should be extended accordingly.
IV. Project Cost and Payment Method
- Total Cost: It can be calculated based on the unit price per square meter of building area (e.g., 800 yuan per square meter for the main house and 600 yuan per square meter for the auxiliary house) or a total amount can be directly agreed upon.
- Payment Method: Payments are usually made in stages, such as a 30% advance payment after contract signing, 20% after foundation inspection, 40% after the main structure is completed, and a 10% final payment after project completion and acceptance. The proportion and payment conditions for each stage should be clearly specified.
V. Project Quality and Inspection Party B must construct according to Party A's drawings and national standards. Key processes (such as foundation work and concrete pouring) must be inspected and approved by Party A and safety management personnel before proceeding. Both parties must sign off on the completion inspection, and Party A must submit the contract, drawings, inspection records, and other materials to the township government for archiving within 15 days.
VI. Responsibilities of Both Parties
- Party A's Responsibilities: Provide infrastructure such as water, electricity, and roads necessary for construction, make payments as agreed, and supervise project quality.
- Party B's Responsibilities: Ensure the project duration and quality, comply with safety regulations, assume responsibility for injuries, fatalities, and third-party damages during construction, and provide a one-year warranty service.
VII. Liability for Breach of Contract
- If Party A fails to make payments as agreed, Party B has the right to halt construction, and the project duration will be extended accordingly.
- If Party B's construction quality is substandard, rework and associated costs will be required. If the project is not completed on schedule, a penalty (e.g., 100,000 yuan, subject to adjustment by the court based on actual losses) will be imposed.
- Matters not explicitly agreed upon (such as the price of roof eaves) can be handled according to local trading practices or court rulings.
VIII. Other Matters Any matters not covered in the agreement can be negotiated and supplemented separately. The agreement shall be made in duplicate, with each party holding one copy, and shall take effect upon signature and sealing. It is recommended to refer to the 'Civil Code of the People's Republic of China' and relevant local regulations (such as the 'Regulations on the Self-built Housing of Rural Villagers in Jiangxi Province') to完善 [此处中文原文“完善”在英文语境下应处理为“完善条款”的对应英文“improve the clauses”,但考虑到整体流畅性,直接译为“完善相关内容”的“refine the relevant content”意思也通,不过更贴合原文直接意思的是补充说明参考法规来“完善条款”,这里按更贴合原文直接表意处理] refine the relevant content of the clauses.