The construction of outdoor mobile toilets in Ningxia requires customized plans based on specific needs, with the construction process covering site selection, design, bidding, construction, and acceptance, and featuring flexible material and functional configurations.

I. Construction Process and Duration
Taking the project in the Pingfang District of Xingying Eighth Team, Xixia District, Yinchuan City as an example, the construction duration is approximately 5 months:
- Preliminary Preparations: Site selection was completed in March 2025, taking into account factors such as pedestrian traffic, sewage disposal conditions, and the surrounding environment. Design plans and budgets were finalized in April, specifying functional zones (such as squatting stalls, management rooms, and intelligent control rooms) and material selection.
- Bidding and Commencement: The bidding announcement was issued on June 20th to determine the construction unit. Construction officially commenced on July 9th, with the main structure adopting a composite steel structure, covering an area of 28 square meters and including 6 unisex squatting stalls.
- Construction and Acceptance: Construction was completed on August 12th, and the project passed acceptance and opened for operation on August 15th. Acceptance criteria included structural stability, functionality of the intelligent system, and compliance with sewage disposal regulations.
II. Customized Configuration Options
The construction of mobile toilets in Ningxia supports multi-dimensional customization:
- Skeleton and Walls: The skeleton can be selected from steel structural dragon skeletons or stainless steel columns, while the walls adopt galvanized pipe dragon skeletons + fire-resistant painted panels, balancing strength and fire resistance.
- Ventilation and Roofing: Ventilation methods include natural ventilation, exhaust fans, or hollow straight exhaust; the interior ceiling uses PVC ceiling panels or aluminum alloy扣板 (gusset plates), while the exterior roof adopts high-quality waterproof materials suitable for outdoor environments.
- Flooring and Sewage Disposal: Flooring options include concrete panels or hard floors, and the sewage disposal system supports water flushing and direct drainage (requiring connection to municipal sewage networks) or waterless packaging (suitable for water-scarce areas).
- Intelligent Functions: An intelligent control system can be integrated to enable automatic flushing, air quality monitoring, remote management, and other functions, enhancing the user experience.
III. Key Considerations
- Compliance: Construction must comply with local environmental protection and building regulations in Ningxia, especially the sewage disposal system, which must pass approval from the environmental protection department.
- Maintenance Convenience: Maintenance access channels should be reserved during design, and materials should be selected for corrosion resistance and ease of cleaning to reduce long-term maintenance costs.
- Adaptability: Configurations should be adjusted according to climatic conditions, such as adding insulation layers in cold winter regions and reinforcing wall sealing in windy and sandy areas.