Whether it is feasible to cut horizontal slots in prefabricated houses depends on the situation and cannot be generalized.

1. Prefabricated slab floors: Cutting horizontal slots horizontally is strictly prohibited Prefabricated slab floors are composed of prefabricated concrete slabs joined together, and their structural integrity relies on the continuity of the slabs themselves. Cutting horizontal slots across the slabs will directly disrupt the load-bearing system of the floor, leading to a decrease in the floor's load-bearing capacity and even the risk of cracks or collapse. Regulations only allow longitudinal slotting along the slab joints, and the depth of the slots must not exceed one-third of the slab thickness to ensure the structural safety of the slabs.

2. Load-bearing walls in prefabricated slab buildings: Cutting horizontal slots is a violation Load-bearing walls are the main load-bearing components of a building, and their stability directly affects the overall structural safety. Cutting horizontal slots in load-bearing walls, especially those exceeding a certain length limit (such as 10 meters), will significantly weaken the wall cross-section, reduce its shear and bending resistance, and may cause wall deformation or structural instability. According to Article 5 of the 'Measures for the Administration of Interior Decoration and Renovation of Residential Buildings (Revised in 2011)', altering the main structure and load-bearing components of a building without professional assessment and approval is an illegal act.

3. Non-load-bearing floors: Careful and limited slotting is allowed, but strict regulations must be followed Non-load-bearing floors (such as some partition floors) bear less load and can be slotted with caution, but the following conditions must be met:

  • Check the structural drawings in advance: Confirm the floor type, the position of reinforcing bars, and the distribution of pipelines to avoid the load-bearing reinforcing bars and existing pipelines;
  • Control the slotting depth: The depth must not exceed one-third of the floor thickness to avoid damaging the structural layer;
  • Limit the horizontal length: The total length should not exceed one-fifth of the floor span to prevent local stress concentration;
  • Repair promptly: After slotting, fill it with high-strength materials to restore the structural performance of the floor.

Operational advice: Regardless of the situation, consult a professional architect or structural engineer before slotting. Assess the feasibility through on-site inspection or calculation and analysis to ensure compliance with building regulations. Unauthorized slotting may cause safety hazards and should be treated with caution.