Yangzhou Prefabricated Assembly House
Yangzhou boasts multiple representative projects in the field of prefabricated assembly houses, with a mature technological system and wide application. By 2026, the proportion of prefabricated buildings had reached 43.6%, higher than the average level in Jiangsu Province.

I. Typical Project Practices
NO.2025G11 Plot Project
Located in the core area of Longchuan South Road, Jiangdu District, the project covers a total construction area of 65,000 square meters with a total investment of 360 million yuan. It is undertaken by Jiangsu Yangzhou Construction Engineering Group Co., Ltd. The project adopts a prefabricated concrete structure (PC structure), covering the entire chain of construction including residential buildings, supporting facilities, and underground garages. It is a key prefabricated high-quality residential benchmark project promoted in Jiangdu District in 2026, with a construction period of 450 days and a winning bid price of approximately 332 million yuan.Baoying 2024JY22 Plot Project
Located on the north side of Jincheng Road and the west side of Dongyang Road, the project covers a total construction area of 114,200 square meters with an estimated construction contract value of 500 million yuan and a planned construction period of 750 calendar days. The project explicitly adopts prefabricated building technology and is developed by Yangzhou Yiyuan Real Estate Co., Ltd. with funding from state-owned capital. The construction scope covers the entire process including civil engineering, installation, decoration, and fire protection, demonstrating the application of prefabricated buildings in large-scale comprehensive projects.Tianshan Xincun Resettlement Area Phase II Project
As the first prefabricated concrete structure residential building project in Yangzhou City, it is constructed by Jiangsu Huajiang Construction Group Co., Ltd. The project features a 17-story frame-shear wall structure with a prefabrication rate of 47%. It utilizes prefabricated prestressed composite slabs, prefabricated beams, prefabricated stairs, and other components, and applies BIM technology for information-based construction. It has been approved as a "Jiangsu Provincial Green Construction Demonstration Project" and a "Ministry of Housing and Urban-Rural Development Green Construction Demonstration Project," providing a benchmark case for the promotion of prefabricated building technology.
II. Development Scale and Types in 2026
In 2026, the newly started construction area of prefabricated buildings in Yangzhou City exceeded 4.87 million square meters, accounting for 43.6% of newly constructed buildings, which is 5.2 percentage points higher than the average level in Jiangsu Province. The project types cover three major areas:
- Affordable Housing: Such as the "**** Yuan (Han) Project in Hanjiang District, Yangzhou City," which adopts a composite system of composite slabs + prefabricated stairs + ALC wall panels to enhance living quality and construction efficiency.
- Educational Public Buildings: Such as the "**** School (Guang) Project in Guangling District, Yangzhou City," which requires a prefabrication rate of no less than 50%. The steel structure modular classrooms are an independent procurement package, promoting the standardization of public building construction.
- Industrial Carriers: Such as the "**** Intelligent Manufacturing Park (Kai) Project in Yangzhou Economic and Technological Development Zone," whose Phase I plant adopts a "steel frame + prefabricated concrete roof + integrated curtain wall," demonstrating the adaptability of prefabricated buildings in the industrial sector.
Through policy guidance and technological innovation, Yangzhou has formed a multi-type prefabricated building system covering residential, public, and industrial buildings, providing replicable experience for the transformation of the construction industry towards industrialization.