The installation of mobile toilets in Nantou requires selecting the appropriate process based on the toilet type (integrated or split-type). The core steps include positioning and foundation treatment, main structure assembly, facility connection, and functional testing, as detailed below:

I. Positioning and Foundation Treatment
- Site Planning: Determine the installation location based on usage needs, prioritizing areas with solid ground and good drainage, avoiding low-lying areas prone to water accumulation or soft soil.
- Foundation Reinforcement: If the ground is uneven or soft, harden it in advance (e.g., by pouring concrete) or lay steel plates to ensure structural stability after installation. For example, split-type toilets, due to their greater weight, have higher requirements for foundation flatness.
- Drainage Planning: If connection to municipal sewage networks or dedicated septic tanks is required, reserve pipeline interfaces in advance and ensure proper slope; waterless or biodegradable toilets can simplify this step.
II. Main Structure Assembly
- Split-Type Toilets:
- Chassis and Frame Installation: Use a forklift or manual labor to place the prefabricated steel chassis steadily, adjusting it to a level state with a level gauge to avoid tilting during subsequent use.
- Wall and Roof Panel Fixation: Insert the sandwich panel walls into the chassis slots and secure them with bolts or clips; after installing the roof panels, seal the gaps (e.g., with caulking) to prevent rainwater leakage.
- Integrated Toilets (e.g., Container Toilets):
- The factory has completed interior decoration and equipment integration. On-site, simply hoist the entire unit to the designated location with a crane, then connect water, electricity, and sewage pipelines. Installation time can be reduced to 2-4 hours.
III. Internal Facility Connection
- Equipment Installation: Fix toilets, flushing systems, sinks (if any), lighting, and ventilation equipment, ensuring reasonable positioning and ease of use.
- Pipeline Connection: Use modular quick connectors to connect water and electricity pipelines, shortening installation time. However, this should be done by professionals to avoid water leakage or short-circuit risks.
- Special Type Handling: For waterless toilets, install biodegradation devices; for solar-powered toilets, debug the photovoltaic panels and energy storage systems.
IV. Functional Testing and Debugging
- Flush Testing: Check the flushing force and drainage speed to ensure no blockages or leaks.
- Circuit Testing: Test the power supply stability of lighting, ventilation, and smart devices (e.g., sensor faucets).
- Seal Testing: Focus on checking wall joints, doors and windows, and sewage pipeline connections to prevent odor leakage.
Precautions:
- Installation must comply with standards such as the Hygiene Code for Mobile Toilets (GB/T 21239-2023) to ensure structural safety and hygiene compliance.
- Specific installation methods may vary slightly depending on the model. It is recommended to contact the manufacturer or a professional team for targeted guidance to avoid equipment damage or safety hazards due to improper operation.