The installation of mobile toilet accessories requires standardized operations in stages, with core procedures and precautions as follows:

I. Pre-installation Preparations
Material Inventory and Inspection
- Verify the quantity, model, and accessory list of the mobile toilet unit (such as sinks, flushing devices, sewage pipes, curtains, non-slip mats, etc.), ensuring the equipment has no visible damage and internal facilities function properly.
- Focus on checking the completeness of smart toilet accessories (such as flange rings, installation templates, water inlet pipes, power cords) to avoid rework due to missing parts.
Tool and Personnel Preparation
- Equip with tools such as wrenches, screwdrivers, spirit levels, and caulking guns. If the toilet unit is heavy, coordinate with a crane for assistance in handling.
- Arrange 2-3 professional installers, with at least one person familiar with water and electrical connections.
II. On-site Installation Steps
Foundation Fixing
- Use a crane to lift the toilet unit to the designated location and adjust its levelness with a spirit level, ensuring the deviation is ≤3mm.
- Secure the equipment with expansion bolts (for concrete foundations) or counterweights (for soft soil foundations). In areas with strong winds, additional anti-tipping measures are required.
Water and Electrical Connection and Debugging
- Sewage Pipe Connection: Connect the pipe to the sewer or collection tank, ensuring a slope of ≥2% to prevent sewage backflow; reinforce the connection with sealing rings to prevent leakage.
- Water Supply Connection: Use a water pipe ≥DN20 to connect to the flushing device and test the water pressure for stability; debug the flushing function and check the drainage seal (e.g., no odor from floor drains).
- Smart Toilet Water and Electrical Reservation: If equipped with a smart toilet, confirm the pit distance (305mm/400mm±10mm), power outlet (pre-embedded 86 junction box within 30cm of the sewage outlet center), and cold water pipe position in advance.
Detail Inspection and Cleaning
- Install accessories such as curtains, non-slip mats, and air freshener boxes, and test the flexibility of door locks and flush buttons.
- Thoroughly clean and disinfect the interior of the toilet and place consumables such as toilet paper and trash bags.
III. Special Installation Points for Smart Toilets
Base Surface Treatment
- Do not use cement mortar to fix the toilet; use silicone sealant or a flange ring for sealing. If the original pit is uneven, adjust it to level with shims.
Installation Process
- Removal and Cleaning: Close the water inlet angle valve, remove the old toilet, and block the sewage pipe opening. Release water for 3-5 minutes to empty pipe impurities.
- Positioning and Fixing: Align the installation template with the centerline of the sewage outlet, draw the outline, and install the flange ring; slowly lower the toilet and tighten the fixing bolts (avoid over-tightening to prevent cracking).
- Function Debugging: Connect the water inlet pipe and power supply, and test whether the smart functions such as flushing, heating, and drying work properly.
Precautions: Wear protective gloves during installation to avoid cuts; if the pit distance does not match or there are errors in water and electrical reservations, contact the supplier promptly for adjustments and do not force installation.