The installation steps for mobile environmental toilets in Jurong are as follows:

Preliminary Planning and Preparation

  1. Site Assessment and Selection: Conduct an on-site survey of the proposed installation location to evaluate ground flatness, soil conditions, distribution of underground pipelines, surrounding drainage conditions, and vehicle access. The site should avoid low-lying areas prone to water accumulation and choose a solid, flat surface to ensure convenient subsequent cleaning services.
  2. Determine Model and Specifications: Based on the usage scenario (such as parks, construction sites, event venues), pedestrian traffic, and treatment requirements (such as whether to connect to municipal sewage networks), select treatment technologies such as packaged, biodegradable, or circulating water flushing types, and specify the equipment model.
  3. Obtain Necessary Permits: Comply with the regulations of the site management authority and complete site usage reporting or approval procedures to ensure compliance with installation regulations.
  4. Tool and Material Preparation: Prepare tools such as level gauges, wrenches, screwdrivers, and electric drills, and check whether components such as toilet bodies, septic tanks, pipelines, and fasteners are complete and intact.

Foundation Treatment

  1. Ground Leveling: Remove debris (such as stones and branches) from the site and perform preliminary leveling of uneven ground.
  2. Foundation Construction:
    • Concrete Foundation: For long-term fixed sites, pour a concrete platform, reserve anchor bolts or fixing holes, and install after the concrete has fully solidified.
    • Gravel Cushion Foundation: For temporary or soft soil sites, lay and compact gravel to enhance foundation bearing capacity and drainage.
    • Special Brackets or Bases: Some mobile toilets are equipped with adjustable steel brackets, which need to be placed horizontally and fixed to the ground.

Main Body Positioning and Fixing

  1. Lifting and Transportation: Use a forklift or crane to transport the toilet body smoothly, avoiding collisions that could damage the structure and internal facilities.
  2. Placement and Alignment: Lift the toilet body onto the foundation and slowly lower it to ensure full contact with the bottom. Use a level gauge to measure in multiple directions and adjust to a horizontal state (leveling can be achieved by adjusting base screws or adding steel plates).
  3. Main Body Fixing: Fix the toilet body according to the foundation type. For pre-embedded bolt foundations, align the holes and tighten with nuts; for other foundations, use expansion bolts to fix to the concrete or enhance wind resistance with steel cables or ground anchors (especially important in windy areas).

Pipeline and Treatment System Connection

If connecting to an underground fecal storage tank or municipal sewage network, ensure that the pipeline dimensions match, use special sealing rings or sealants at the joints, and maintain an appropriate slope for pipeline laying to prevent the retention or leakage of waste.