The installation of mobile public toilets in Hebei should follow the following procedures and key points:

I. Pre-installation Preparation
- Site Assessment: Conduct an on-site inspection of the usage area, focusing on ground flatness, surrounding passage width, and water and electricity access conditions. If the ground is soft soil, it should be hardened in advance or covered with a gravel bed; at the same time, reserve space for equipment transportation and lifting to ensure construction convenience.
- Material and Specification Selection: Choose materials based on budget, usage cycle, and environmental conditions, such as color-coated steel plates, fiberglass, metal carved panels, or plastic integrated molding; for specifications, standard options like single-person or double-person models are available, or custom sizes can be made according to actual needs.
- Product Type Adaptation:
- Water-flush Type: Requires connection to water supply and drainage pipes, suitable for areas with stable water supply and sewage disposal conditions, offering a user experience similar to home toilets.
- Waterless Packing Type: Does not require a water source; uses special packing bags to collect waste, suitable for remote areas lacking water or unable to connect to sewage pipes.
- Foam Sealing Type: Uses foam instead of water for flushing, combining water-saving and odor-control advantages, suitable for scenic spots, parks, and other high-traffic areas requiring water conservation.
II. Installation Process
- Lifting and Fixing of Main Structure:
- Adopt factory-prefabricated modular structures, transported to the site and lifted using lifting equipment.
- Use a level to calibrate the box posture to ensure it is level; choose fixing methods according to site conditions, such as welding pre-embedded parts for concrete foundations or using expansion bolts for hardened ground; add waterproof sealing strips at box connections to prevent leakage.
- Installation of Water Supply and Drainage Systems:
- For the water supply system, select insulated pipes according to water temperature, bury pipes deeper than the frost line, and install filtration devices on the inlet pipes.
- For the drainage system, lay pipes according to slope requirements, connecting to septic tanks or municipal sewage networks; in cold areas, drainage pipes should be wrapped with insulation materials and set with drainage slopes to prevent freezing and cracking.
- Configuration of Electrical and Ventilation Systems:
- For circuit wiring, use waterproof cables, with switches and sockets meeting splash-proof ratings, and prefer low-voltage LED lighting systems.
- For the ventilation system, determine the number of air changes according to the number of users, install louvers on side walls or add exhaust fans to ensure air circulation.
III. Post-installation Inspection and Maintenance
- System Testing: Include checks on the sensitivity of flushing devices, pipe pressure tests, circuit insulation resistance measurements, and ventilation equipment operation tests to ensure all systems are functioning properly.
- Regular Maintenance: Establish a maintenance plan, including checks for pipe freeze protection, replacement of aged sealing strips, anti-corrosion treatment of metal parts, etc., to extend service life.
IV. Special Environmental Handling
Considering Hebei's climatic characteristics, for winter installations, understand the soil freeze-thaw cycle in advance and appropriately deepen pipe burial depths; in windy areas, install windproof cable fixing devices; prepare temporary rain shelters for construction during the rainy season to prevent internal equipment from getting wet.
V. Safety Measures
Set up warning areas during lifting operations, with operators holding relevant certificates; use safety belts and protective nets for high-altitude work in accordance with regulations; strictly follow the principle of separating strong and weak currents in electrical installations, with all cables threaded through flame-retardant tubes for protection; equip the site with firefighting equipment and set up clear warning signs in hazardous areas.