Zhejiang Prefabricated House Construction

Admin 18 de septiembre de 2026

Taking a project in Xiaoshan District, Hangzhou, Zhejiang as an example, the prefabricated house construction in Zhejiang features standardization, efficiency, and environmental protection. Its construction process, technological advantages, and climate adaptability design are noteworthy.

I. Construction Process and Organization

The project covers a total construction area of 12,000 square meters and consists of six three-story prefabricated residential buildings. It adopts a prefabricated concrete frame structure with a prefabrication rate of 75%. The construction is divided into six stages:

  1. Preliminary Preparation (Days 1-15): Complete site leveling, temporary facility setup, and surveying and staking out to lay the foundation for subsequent construction.
  2. Component Production (Days 16-75): Simultaneously carry out detailed design of prefabricated components, mold making, and factory production. The main components include prefabricated columns, composite beams, composite floor slabs, stairs, and external wall panels.
  3. On-site Assembly (Days 61-150): Conduct flow construction building by building. Each building is assembled in the order of 'foundation → prefabricated columns → prefabricated beams → composite slabs → stairs → external panels', with each floor's construction cycle controlled within 5 days.
  4. Mechanical and Electrical Installation (Days 101-165): Intersperse pipeline embedding and equipment installation with assembly construction to shorten the project duration.
  5. Decoration and Finishing (Days 136-175): Complete interior and exterior wall plastering, door and window installation, and floor paving, with a focus on finished product protection.
  6. Completion Acceptance (Days 176-180): Organize a five-party acceptance to ensure the project quality meets design and regulatory requirements.

II. Technological Advantages and Innovation

  1. Industrialized Production Mode: Components are produced in a factory with standardized processes, ensuring stable quality and high precision. This reduces on-site wet work and lowers construction waste and dust pollution.
  2. BIM Collaborative Design: Optimize component design through a multi-disciplinary BIM model, clarify component numbers and connection nodes, and achieve precise assembly and construction simulation.
  3. Modularization and Structural Integration: Adopt high-strength steel structures or concrete prefabricated components that integrate insulation, sound insulation, and fire protection functions, supporting disassembly and reuse.
  4. Climate Adaptability Design: In response to Zhejiang's rainy and humid climate, factory production avoids weather impacts on construction, ensuring component quality and project schedule stability.

III. Construction Machinery and Efficiency Improvement

Equip with tower cranes, truck cranes, construction elevators, and other equipment to achieve efficient lifting and transportation of components. Through a flow operation method of 'prefabricated component lifting → node connection → mechanical and electrical embedding → concrete pouring', combined with construction zoning and flow section division, the project duration is shortened by more than 50%, significantly improving construction efficiency.