How to Remove a Movable Corner in the Toilet

Admin 19 de octubre de 2026

The removal of a movable corner in the toilet should be handled differently based on its specific structure, mainly divided into two categories: panel removal and wall relocation. Here are the specific steps and precautions:

I. Panel Removal (for ceiling or wall decorative panels)

  1. Locate the Seam Position The panels of the movable corner are usually fixed with clips, and the seam (the starting point for installing the last panel) is mostly located at the edges on both sides of the corner. First, observe the gaps between the panel joints to find the hidden clip structure. If it is an aluminum panel, the seam may have decorative lines; PVC panels may be engaged through grooves.

  2. Loosen and Remove the End Panel Gently push the last panel at the seam with your hand to separate it from the clip. If the clip is tight, insert a plastic scraper or a thin tool along the gap to avoid scratching the panel surface. After loosening, slowly remove the panel to one side (usually perpendicular to the joint seam) to prevent the clip from breaking.

  3. Remove the Remaining Panels in Sequence After removing the end panel, the other panels lose their fixed constraints and can be removed one by one in reverse order of installation. If some of the middle panels are fixed with screws (common at corners or reinforcement points), use a screwdriver to unscrew the screws before removal.

II. Wall Relocation (for movable partition walls)

  1. Assess the Structural and Functional Impact Before relocation, confirm whether the wall carries drainage pipes, vents, or electrical wiring. If it involves concealed work, turn off the water and power supply in advance and mark the positions of the pipes to avoid damage during construction. For example, when moving a wall near the toilet, check whether the drainage riser is embedded in the wall.

  2. Damp-proof Treatment The toilet environment is humid. After relocation, the bottom of the new wall should be painted with waterproof coating (such as polyurethane waterproof coating) to a height of not less than 30 centimeters. If light steel keels or wooden materials are used, a damp-proof membrane should be laid at the point of contact with the ground to prevent moisture penetration and deformation.

  3. Choose the Relocation Method

    • Bricklaying Method: Suitable for walls that need to be permanently fixed. Build with bricks according to the design drawings, applying cement mortar between each layer of bricks. The top of the wall should be filled with sloping bricks where it meets the ceiling to enhance stability.
    • Light Steel Keel Method: Suitable for lightweight walls that can be quickly assembled and disassembled. Build a frame with light steel keels (the main keels are spaced 60 centimeters apart, and the secondary keels are spaced 40 centimeters apart), cover with gypsum board and fix it with screws, and apply牛皮纸 (kraft paper) at the joints to prevent cracking.
    • Partition Method: If only temporary space division is needed, wooden boards, glass, or gypsum board can be used to directly make partitions, which are fixed to the ground and ceiling with metal brackets or expansion bolts.
  4. Safe Construction Points Wear goggles and gloves during the relocation process to prevent injury from brick debris or metal. If using power tools (such as an electric drill), ensure good grounding to avoid electric shock. After relocation, clean the site in a timely manner, maintain ventilation, and accelerate the evaporation of moisture.