Volver al blog
Artículo

Tieling Prefabricated Assembled Housing

Admin 18 de septiembre de 2026

Tieling's prefabricated assembled housing has developed rapidly, forming a pattern of multiple project implementations and diverse type coverage.

I. Development Status
According to the 2026 report from the Liaoning Provincial Department of Housing and Urban-Rural Development, the proportion of newly started construction area for prefabricated buildings in the province reached 42.7%, with Tieling City leading in northern Liaoning with an average annual growth rate of 31.5%. Its application scope covers Yinzhou District, Diaobingshan City, Fanhe New District, and Kaiyuan Economic Development Zone. The technical systems include composite floor slabs, prefabricated shear walls, integrated kitchen and bathroom systems, etc. Most projects are in the middle to late stages of main structure construction.

II. Progress of Typical Projects

  1. Projects Under Construction

    • Tieling Central Tower A: Construction started in October 2025. Currently, the 8th-floor prefabricated stairs are being hoisted, and ALC internal partition walls are being installed. The procurement of supporting facilities has initiated the selection process for secondary detailed design units.
    • Kaiyuan School: Adopting the EPC general contracting model, the first teaching building was capped in February 2026, with a prefabrication rate exceeding 55%. Exterior wall cladding and composite beams have arrived on site, and the procurement of door and window systems is underway.
    • Diaobing Apartments: Pile foundations were completed in December 2025, and standard floor construction began in March 2026. Stairs, balcony slabs, etc., are directly supplied by local component factories, with on-site assembly efficiency reaching two floors per day.
  2. Planned Projects

    • Tieling Hospital: Planned with a construction area of 98,000 square meters and a prefabrication rate of no less than 60%, including an outpatient building and an inpatient building. The structural type is an assembled monolithic concrete frame-cast-in-place shear wall. The survey and design bidding announcement was released in March 2026.
    • Xifeng Industrial Park: The first phase includes three standardized factory buildings adopting a steel structure prefabricated system. The procurement of roofing systems, enclosure wall panels, and other materials gives priority to the local supply chain.
    • Changtu Community: Twelve affordable housing units have a prefabrication rate of 65%, including prefabricated internal walls and integrated bathroom modules. The general contracting bidding is expected to start in the third quarter of 2026.

III. Products and Enterprises
Xibang Jiamei (Qingzhou Xibang Industrial and Trading Co., Ltd.) provides materials such as decorative insulation integrated panels and metal carved panels. Among the prefabricated housing products of Liaoning Tieling Jiamei, the price for prefabricated toilets in light steel school buildings is 1,300 yuan for areas ≥300 square meters, and for vacation houses and scenic area homestays, it is 1,350 yuan for sets ≥50.

IV. Other Types
Integrated housing is based on a modular concept, using light steel structures and composite panels with internal insulation materials. K-type panel houses use light steel structures as frames and composite sandwich panels as enclosure structures, featuring fast construction, low cost, and strong environmental protection. They have expanded into fields such as emergency relief and commercial retail.