The installation of a sunshine container house mainly involves steps such as bottom frame installation, main frame construction, wall and door/window installation, and sunroom module installation. Here is a detailed introduction:

Bottom Frame Installation

  • Connect the bottom corners and bottom beams: On a flat ground or workbench, connect the bottom corners of the container to the bottom beams using hexagon socket bolts, but do not tighten them temporarily.
  • Square adjustment and fastening: After square adjustment, ensure that the diagonal difference of the bottom frame is ≤3mm, and then tighten the bolts.
  • Install secondary beams: Install π-shaped secondary beams according to the positions of the positioning holes on the long beams and fix them with m5.519 self-tapping screws. The top of the π-shaped secondary beams needs to be fixed with st4.816 round-head self-drilling screws to the bottom beams.
  • Lay the floor base plates: Lay the floor base plates (magnesium oxide boards) along the 6-meter direction. The base plates at both ends have been pre-punched, but they need to be cut at an angle according to the drawn chalk lines.
  • Mark and lay the floor: Mark the midline of the π-shaped beams and start laying the floor from one end. The joint between two floor panels should coincide with the midline of the π-shaped beams. After laying the floor, snap chalk lines on the floor according to the previously marked midline of the π-shaped beams (two chalk lines are required at the floor panel joints, each deviating 20mm from the midline), and fix the floor panels with st4.2*38 cross-head self-tapping screws along the chalk lines, with a nail spacing of 300 - 350mm.
  • Floor treatment: Sand the entire floor, especially the panel joints, apply PVC special floor adhesive, wait for 10 - 15 minutes, lay the floor covering, and expel the air between the floor covering and the base plate. If possible, perform welding treatment on the joints of the floor covering.

Main Frame Construction

  • Inspection and hoisting: For foldable container mobile homes, check the stability of the steel wire ropes during installation. Hoist the main frame, unfold it smoothly, and then place support rods in the middle of the container body to keep it stable.

Wall and Door/Window Installation

  • Install the walls: Push open one wall and tighten it with fastening screws, then push open the other wall with doors and windows and tighten the screws.

Sunroom Module Installation

  • Track and sliding rail system: Install a sliding rail system on the track for the movable sunroom, which adopts a telescopic folding design. There are two opening and closing methods: manual and electric. If the movable sunroom is small in size, it can be designed as a manual type; if the area is large, an electric type is recommended, equipped with a remote control for one-button opening and closing. At the same time, add safety locks to ensure that the sunroom module is fixed and does not shake.