Shenzhen Prefabricated House Budget

Admin 18 de septiembre de 2026

The comprehensive budget for prefabricated houses in Shenzhen is approximately 2019 yuan per cubic meter, with pre-tax revenue of 2363 yuan per cubic meter, a gross profit of 344 yuan per cubic meter, and a profit margin of about 14.4%. However, the actual budget needs to be adjusted according to the specific circumstances of the project.

Cost Composition Analysis

  1. Factory Construction Amortization The self-built production line is located in a 4000㎡ prefabrication factory, with infrastructure investment of approximately 2 million yuan. After straight-line amortization over 5 years, the amortized cost per cubic meter of prefabricated components is about 20 yuan. Adding mold amortization, the overall amortization cost reaches 28 yuan per cubic meter.

  2. Raw Materials and Building Material Consumption Concrete and steel bars are the main materials. The consumption of C30 concrete is 1.02 cubic meters per square meter, and the usage of steel bars is about 110 kg per cubic meter. The cost of auxiliary materials (release agents, lifting pins, welding rods, etc.) is about 50 yuan, with a total material cost of approximately 1000 yuan per cubic meter.

  3. Freight and Logistics The combined transportation and lifting/loading/unloading costs are 100 yuan per cubic meter, which need to be adjusted according to the transportation distance and lifting difficulty.

  4. Labor Costs Assuming workers work 8 hours a day, the average daily comprehensive cost is about 2500 yuan, with a labor cost per cubic meter of 100 yuan. If the project scale expands or the construction period is tight, labor costs may increase.

  5. Machinery and Energy The rental cost of equipment such as overhead cranes and mixing stations is about 200,000 yuan per month. The electricity cost for production is about 20 yuan per cubic meter, and the energy consumption of fuel-powered machinery is 30 yuan per cubic meter, with a total cost of 250 yuan per cubic meter. Fluctuations in equipment efficiency or energy prices will affect this part of the cost.

  6. Taxes and Management The total taxes payable per cubic meter of concrete are about 338 yuan, and the management fee is 5% of the output value, which is 133 yuan per cubic meter. Changes in tax policies or management efficiency will directly affect costs.

  7. Hidden Costs and Profits Hidden costs include a tea fee of 50 yuan and a risk deposit of 20 yuan, totaling 70 yuan per cubic meter. The expected profit is set at 214 yuan per cubic meter, which needs to be adjusted according to market competition and project risks.

Actual Budget Considerations

The above budget is based on a specific project scale (two 29-story residential buildings, each with an area of 460 square meters per floor, and a prefabrication volume of about 1000 cubic meters). The actual budget needs to consider factors such as project scale, design complexity, material price fluctuations, and construction period requirements. For example, small-scale projects may have higher amortization costs, while large-scale projects may reduce material costs by optimizing the supply chain.