Rapid Installation Methods for Prefabricated Houses

Admin 18 de septiembre de 2026

There are three main rapid installation methods for prefabricated houses: prefabricated rapid-installation house structures, prefabricated assembly hoisting construction plans, and installation details for prefabricated panels in self-built houses, as detailed below:

Prefabricated Rapid-Installation House Structures: Place prefabricated columns at the four corners of the house's main body. The prefabricated beams are inserted into the slots at both ends through the clips around the prefabricated columns and fixed between them. The prefabricated walls are fixed on all four sides of the house's main body by inserting the plugs on the top and bottom edges into the holes in the prefabricated beams. Finally, lay the prefabricated floor slabs on top of the prefabricated beams. The advantage of this method is that the building components are pre-processed in the factory and directly assembled on-site, reducing construction procedures and significantly shortening the construction period.

Prefabricated Assembly Hoisting Construction Plan:

  • Process Flow: First, prepare for the installation of prefabricated wall panels, then use hoisting equipment to lift the prefabricated wall panels, quickly position them, install diagonal supports, make fine adjustments, install fixed corner brackets, pour structural concrete, and finally apply sealant for finishing.
  • Pre-Installation Preparation: Precisely process positioning reinforcement to ensure that the positioning dowels of the prefabricated walls can be accurately and quickly inserted into the columns; the wall concrete must be inspected and signed off by multiple departments before pouring; accurately position and mark lines on the cast-in-place surface layer of the floor slab according to the embedded bolt positioning diagram.
  • Hoisting Key Points: Use modular hoisting beams, select lifting points based on the position of the lifting rings, and connect the steel wire ropes to the lifting rings with shackles; slowly lift to about 500mm above the ground to inspect the appearance and lifting ring connections; steadily lift with a truck crane, and when the wall panel is about 600mm above the working layer, construction personnel use a tag line to control the descent speed.
  • Diagonal Support Installation: Connect the diagonal support rods to the connectors or steel reinforcement loops on the prefabricated wall panels and the cast-in-place slabs with bolts, make initial adjustments to keep the wall panels roughly vertical, and temporarily fix them in place with adjustable diagonal support bolts.
  • Precise Wall Panel Adjustment: Use long and short diagonal support adjustment rods for calibration in multiple directions; horizontal position adjustment parallel to the wall panel is done by snapping control lines and using a small jack for fine-tuning; horizontal position adjustment perpendicular to the wall panel mainly relies on short diagonal supports.

Installation Details for Prefabricated Panels in Self-Built Houses: For base treatment, wet the top of the wall with water the day before hoisting the panels, and carefully level the top of the wall with high-grade cement mortar to ensure the mortar is full and uniform. Regarding panel bottom support and panel joint treatment, provide support under the panels to prevent the prefabricated panels from bending or cracking under their own weight before they fully gain strength, and properly handle the joints between the panels.