Prefabricated Concrete Houses in Jincheng

Admin 18 de septiembre de 2026

The practice of prefabricated concrete houses in Jincheng is mainly reflected in the prefabricated concrete structure houses. Taking a project in the urban area of Jincheng as an example, it demonstrates a high assembly rate and green construction level.

Project Overview and Assembly System

The project has a total construction area of 25,000 square meters, with 18 floors above ground and 2 floors underground. It adopts an integrated prefabricated concrete shear wall structural system, with an assembly rate of ≥60%. The main prefabricated components include:

  • Prefabricated shear wall panels (accounting for 35%): As the main load-bearing components, they achieve efficient production and installation through standardized design.
  • Composite floor slabs (20%): Composed of a 60mm prefabricated layer and a 70mm cast-in-place layer, balancing structural strength and construction convenience.
  • Prefabricated stairs and balcony panels (accounting for 8% and 5% respectively): Prefabricated in the factory in advance to reduce on-site wet operations.
  • Non-load-bearing internal partition panels (12%): Made of lightweight materials to enhance space utilization.

Technology Integration and Green Construction

The project integrates core technologies such as BIM technology and sleeve grouting connections, achieving innovations in three aspects:

  1. Green Construction: By optimizing design to reduce formwork usage, construction site waste is reduced by more than 80%; renewable energy is adopted, with a substitution rate of ≥8%, meeting the two-star green building standard.
  2. Intelligent Construction: Utilizing BIM models for component disassembly (e.g., wall panel dimensions controlled at 3.2m×2.8m, weight ≤12t), a multi-disciplinary collaborative platform is established for clash detection, construction simulation, and progress management.
  3. Quality Control: Key processes such as sleeve grouting and diagonal bracing installation are emphasized for training to ensure the strength of connection nodes; the assembly rate is guaranteed through scoring in three parts: 'main structure + enclosure wall + decoration equipment pipeline'.

Construction Preparation and Component Management

  • Component Disassembly and Stacking: Based on BIM models, disassembly plans are optimized, stacking areas are clearly divided, and strict regulations are in place for the vertical stacking angle of wall panels and the stacking layers of composite slabs (usually ≤6 layers), with foundation bearing capacity requirements to be met.
  • Lifting Equipment Layout: Appropriate equipment (such as tower cranes) is selected based on component weight, and installation positions avoid underground pipelines to ensure construction safety.
  • Production and Transportation: Molds are customized with 8mm thick steel plates, with an error of ≤0.5mm; steel bar processing and concrete curing adhere to high standards; transportation vehicles are selected according to component characteristics, with good finished product protection during transit (e.g., covering with waterproof cloth, securing against slippage).

On-site Installation Process

Construction proceeds in the order of foundation acceptance → prefabricated columns → shear wall panels → composite beams → composite floor slabs → stairs → balcony panels. Wall panel installation requires cleaning the base layer first, adjusting verticality before fixation; after composite floor slab installation, the cast-in-place layer is poured to form an integral structure. Each process must undergo acceptance upon completion to ensure quality compliance with specifications.