For installing floor tiles in mobile toilets, you can refer to the wet-laying method used for bathroom tiles. The specific steps and key points are as follows:

I. Pre-construction Preparation

  1. Substrate Treatment
    Ensure the floor is level and free of cracks. If there are uneven areas, use cement mortar for leveling. Additionally, the waterproof layer must pass a closed-water test to ensure no leakage issues, preventing subsequent problems such as tile hollowing or detachment due to water seepage.

  2. Material Selection
    The water absorption rate of tiles should be less than 3% to reduce the risk of deformation caused by water absorption and expansion. The cement grade should be no less than 32.5, and it is recommended to use tile adhesive to enhance bonding strength, especially in scenarios where mobile toilets may experience vibration or slight displacement.

II. Standard Construction Process

  1. Snap Line Positioning
    Use the doorway as the reference line to lay out the tiles on both sides. Non-whole tiles (such as those that need to be cut for corners) should be prioritized in concealed locations (such as wall corners or behind equipment) to ensure overall aesthetic appeal.

  2. Mortar Mixing Ratio
    The volume ratio of cement to sand should be 1:2.5, with a water-cement ratio controlled between 0.4-0.5. Mortar that is too thin will reduce bonding strength, while mortar that is too dry will be difficult to level. Strictly adhere to the mixing ratio.

  3. Laying Technique
    Follow the principle of "walls first, then floor." Use a "cross-positioning device" to control the gap width (recommended 2-3mm) to ensure uniform gaps. When laying, gently tap the tiles with a rubber mallet to ensure the mortar saturation exceeds 90%, avoiding local hollowing.

III. Key Quality Control

  1. Slope Control
    A slope of 1%-2% should be created at the floor drain position, detected with a level to ensure smooth drainage and prevent water accumulation. Insufficient slope may lead to stagnant sewage, causing odors or bacterial growth.

  2. Hollowing Inspection
    After 24 hours of laying, gently tap the tiles with a hollowing hammer to check for hollowing. The hollowing area of a single tile should be less than 5%; otherwise, it should be removed and relaid to prevent tile breakage or detachment after long-term use.

  3. Curing Requirements
    Avoid walking on the tiles for 72 hours after completion. Water the tiles daily for 7 days to keep the mortar moderately moist and promote strength growth. Insufficient curing may result in poor bonding between the tiles and the substrate, affecting service life.

By following these steps, you can ensure that the floor tiles in mobile toilets are firmly laid, have smooth drainage, and are aesthetically pleasing and durable.