Dazhou Container House Installation

Admin 15 de septiembre de 2026

The installation of container houses in Dazhou requires a combination of professional design, standardized construction processes, and attention to safety considerations. The specific key points are as follows:

I. Pre-installation Preparation

  1. Site Planning
    The ground should be leveled in advance to ensure that the foundation bearing capacity meets the requirements. For container houses used outdoors for long periods, it is recommended to pour concrete piers or lay steel base beams to enhance wind and earthquake resistance. For example, Sichuan Huayi Rongpeng Steel Structure Housing Manufacturing Co., Ltd. pre-embeds drainage pipes in projects to avoid water accumulation issues.

  2. Materials and Tools
    Prepare corresponding accessories according to the type of house:

    • Assembled container houses: Require hexagon socket bolts, π-shaped secondary beams, self-tapping screws, round-head drill tail screws, etc. Floor base plates (such as magnesium oxide boards) need to be pre-processed by cutting corners along the chalk line.
    • Foldable container houses: Check the stability of steel wire ropes and prepare support rods, fastening screws, and lifting equipment.
    • General tools: Electric drills, wrenches, level gauges, chalk line marking tools, etc.
  3. Design Confirmation
    Contact professional manufacturers (such as local Dazhou suppliers 132-815-55802 or Sichuan Shuozhan Zhuoxin Integrated Housing Co., Ltd.) to obtain personalized design plans, clarifying the positions of doors and windows, circuit reserved openings, and structural reinforcement details.

II. Installation Process

  1. Assembled Container Houses

    • Bottom Frame Installation: Connect the bottom corners of the container to the bottom beams. Do not tighten the bolts temporarily. After adjusting the diagonal difference of the bottom frame to be ≤3mm, tighten them.
    • Secondary Beam and Floor Installation: Install the π-shaped secondary beams and fix them. Lay the floor along the centerline mark, aligning the joints with the centerline of the secondary beams. Fix them with cross-head swallowtail screws at intervals of 300-350mm.
    • Floor Treatment: Grind the joints, apply PVC special adhesive, lay the floor covering, and expel air. Weld the joints if necessary.
  2. Foldable Container Houses

    • Lifting and Unfolding: Non-staff members should stay away from the installation area. Use a crane to smoothly unfold the main frame and place the support rods.
    • Wall Fixation: Push open the walls with doors and windows and tighten them with fastening screws to ensure structural stability.
    • Positioning and Placement: Lift and transport to the predetermined position and then lower it, avoiding personnel being under the lifted object throughout the process.
  3. General Reinforcement Measures

    • For outdoor long-term use scenarios, reinforce the corners with steel frames, make concrete piers at the bottom, and use anti-corrosion wood treatment for the exterior walls to enhance durability.

III. Safety and After-sales

  1. Safety Regulations

    • Non-professionals should not enter the operation area during installation. Ensure that there is no one around when lifting foldable container houses.
    • Electrical circuit connections should be completed by electricians to avoid safety hazards caused by unauthorized connections.
  2. Acceptance and Maintenance

    • After installation, check the tightness of doors and windows, the flatness of the floor, and the drainage slope.
    • Contact the manufacturer (such as Sichuan Huayi Rongpeng Steel Structure) for after-sales warranty and regular maintenance to extend the service life of the house.

Tip: Local Dazhou suppliers (such as 132-815-55802) can provide customized services covering the entire process of design, installation, and commissioning. It is recommended to give priority to manufacturers with steel structure construction qualifications to ensure quality.