The dismantling of container house walls requires adherence to professional procedures and safety regulations, with core steps including cutting off pipelines, sequential dismantling, using professional tools, and implementing protective measures.

1. Cutting Off Pipelines and Relocating Facilities

Before dismantling operations, it is essential to disconnect or relocate power sources, electrical wires, water supply lines, gas pipelines, and heating facilities from the walls. This is to prevent safety accidents such as electric shocks and gas leaks during the dismantling process, ensuring the personal safety of construction personnel. For example, in the dismantling of steel structure factories, the primary task of a professional team upon entering the site is to confirm the mechanical relationships between the main load-bearing components, secondary components, and the enclosure system, while also inspecting and handling relevant pipelines.

2. Sequential Dismantling

Operations must be carried out strictly from top to bottom, and methods such as root-searching, hole-digging, or pushing down are not allowed. For tall walls, scaffolding and protective canopies should be erected. In the dismantling of steel structure factories, the general principle is to first remove non-load-bearing enclosure panels and roof tiles, then unload crane beams and roof live loads, and finally perform segmental cutting of steel columns and main beams. This sequence must not be reversed, as it could easily lead to irreversible plastic deformation of the overall structure during the dismantling process.

3. Using Professional Tools

When dismantling container house walls, appropriate professional tools should be used. For example, when removing color-coated steel plates, specialized edge-biting pliers and cutting saws can be used to separate them from the fixed supports, avoiding large-area tearing that could deform the plates and cause injuries.

4. Implementing Protection and Cleanup

During the dismantling process, protective measures should be taken, such as equipping dust suppression devices and implementing wet operations throughout the construction to reduce dust pollution. After dismantling, the enclosure materials should be immediately sorted and stacked, with metal plates and insulation waste placed in separate recycling channels. Companies like Zhejiang Clas House Dismantling Engineering Co., Ltd. ensure that cleanup is carried out simultaneously with dismantling and that waste is cleared daily, effectively reducing the impact on the surrounding environment.