The simple foundation of container houses typically adopts an independent foundation form, elevating the container on pile foundations to achieve the goals of moisture and insect resistance and ease of site leveling. The following introduces three aspects: foundation types, design considerations, and construction precautions:

I. Foundation Types
The foundation of a container house should be selected based on geological conditions, house size, and usage requirements. Common simple foundations include strip foundations or independent pile foundations:
- Strip Foundation: Suitable for single-story container houses with uniform geology and light loads. Concrete strips are poured along the extension direction of the container's bottom frame to directly bear the weight of the container.
- Independent Pile Foundation: Supports the corner fittings of the container through concrete or steel piles driven into the ground, forming a point support system. This type can adapt to soft soil foundations by adjusting pile length to distribute loads and avoid uneven settlement.
II. Design Considerations
- Load Calculation: Consider the self-weight of the container (approximately 2.3 tons for a 20-foot container and 3.8 tons for a 40-foot container), usage loads (personnel, furniture, etc.), and wind and snow loads. For example, a fully loaded 40-foot container can weigh up to 45 tons, requiring the foundation to have sufficient bearing capacity.
- Moisture Protection: The top of the foundation should be at least 300mm above the ground to prevent rainwater backflow. Waterproof membranes can be laid or waterproof coatings applied on the foundation surface to block the upward path of moisture.
- Connection Method: The corner fittings of the container should be fixed to the foundation through bolts or welding. For example, M20 high-strength bolts can be used to connect the corner fittings to steel plates embedded in the foundation, ensuring structural stability.
III. Construction Precautions
- Site Leveling: Before construction, remove debris from the site, backfill with plain soil, and compact it in layers with a compaction coefficient not less than 0.94. For soft soil foundations, replace with a 300mm thick gravel layer.
- Foundation Positioning: Use a total station to accurately set out lines according to the container layout plan, ensuring that the deviation of the foundation centerline does not exceed ±10mm.
- Curing Period: After pouring the concrete foundation, cover it with plastic film for curing for at least 7 days. The container can be installed only after the strength reaches 75% of the design value.
- Corrosion Protection: If the foundation is in contact with corrosive soil, add corrosion inhibitors to the concrete or use epoxy resin-coated steel bars.