Container House Construction Process

Admin 15 de septiembre de 2026

The construction process of container houses mainly includes core steps such as steel structure frame welding, wall and roof panel installation, internal facility configuration, and waterproofing treatment. The specific process is as follows:

1. Steel Structure Frame Welding
Taking a standard 3m×6m residential container as an example, the chassis is welded around the perimeter with 140×50 channel steel, and the crossbeams use 4×8×2.0 square steel with a spacing of 35 centimeters. The columns and roof ring beams are fully welded with 5×5×2.0 square steel to ensure structural stability. For foldable containers, the main frame is lifted by steel wire ropes and then expanded, with support rods installed to maintain stability. Modular containers require frame welding to be completed in the factory, including the processing of hot-dip galvanized cold-formed steel frames, to ensure that the load-bearing capacity meets standards (e.g., a 20-foot container can bear 25 tons).

2. Wall and Roof Panel Installation
Wall and roof panels typically use 50mm thick purification panels (white on both sides), with a reserved position for a 930×1000 sliding window and a 930×2000 specially made color steel plate door. The chassis is laid with 18mm thick building templates, with a load-bearing capacity of up to 200 kilograms per square meter. For assembled container houses, π-shaped secondary beams need to be laid after the bottom frame is installed, and the floor substrate (such as magnesium oxide board) is fixed with self-tapping screws. The floor is laid along the centerline mark, and the joints are fixed with cross-head dovetail screws at intervals of 300-350 millimeters.

3. Internal Facility Configuration
High-grade floor leather or PVC floor glue is laid on the ground to improve waterproofing and aesthetics. Lighting fixtures (located in the middle of the house), switches (beside the door), and sockets (60 centimeters above the ground) are installed, with an air conditioning hole reserved (opposite the diagonal of the door). For functional containers, water and electricity pipelines need to be embedded. For example, packing-box container houses need to be equipped with fire-resistant polyurethane sandwich panels and an independent circuit system.

4. Waterproofing and Detail Handling
Waterproof glue needs to be applied at the joints of windows, doors, and roof panels, with priority given to glass curtain wall special glue (which has 5-6 times stronger waterproof performance than ordinary glue and a lifespan of over 5 years). Foldable containers require all wall screws to be tightened to ensure no gaps after expansion. Assembled container houses need to polish the floor joints and apply special glue, and the joints of the floor glue can be welded.

5. On-site Assembly and Acceptance
After the factory completes the processing of components, they are transported to the site for rapid assembly. For example, two workers can complete the installation of a foldable container in 3 minutes. Modular container houses need to be hoisted into place and then spliced, greatly shortening the construction period. Trial assembly is required before leaving the factory to ensure that the components match correctly. After on-site installation, the structural stability and waterproof performance are checked.