Circuit for Concrete Prefabricated Houses

Admin 18 de septiembre de 2026

During the circuit construction of concrete prefabricated houses, it is essential to focus on construction preparation, construction procedures, and key construction techniques to ensure the safety and reliability of the circuit system.

I. Key Points of Construction Preparation

  1. Technical Preparation

    • Verify the consistency between the water and electricity drawings and the architectural structure drawings, focusing on checking for conflicts between reserved openings, pipeline routes, and prefabricated components. Specify that pipes with a diameter ≥ 50mm require reserved sleeves.
    • Draw a comprehensive pipeline layout diagram, stipulating that the horizontal spacing between strong current, weak current, water supply pipes, and drainage pipes should be ≥ 300mm, and the vertical distance should be ≥ 150mm. BIM modeling optimization is required for crossing sections to avoid routing in the core areas of concrete beams and columns.
    • Prepare construction technical disclosure documents, clarifying the pre-embedding positions, specifications, and construction requirements of the wire conduits, and formulate solutions for technical challenges in advance.
  2. Material Preparation

    • For the strong current system, select YJV-0.6/1kV copper core cables with a cross-sectional area of 2.5-16mm². Use PVC or galvanized steel pipes for the wire conduits. PVC pipes should have flame-retardant and impact-resistant properties, while galvanized pipes should have uniform wall thickness and be free of rust.
    • The pipe diameter of the wire conduits for lighting circuits should be ≥ φ16, and for power circuits, it should be ≥ φ20. Junction boxes, switch boxes, etc., should match the equipment. Auxiliary materials such as pipe clamps and glue should be provided with quality certificates and inspection reports.
  3. Equipment and Personnel Preparation

    • Equip with tools such as water drill hole openers, hot melt welders, and electrician multimeters to ensure construction accuracy.
    • Construction personnel should hold vocational qualification certificates, receive safety training, and have clear job responsibilities. Establish a quality management system.

II. Construction Procedure Specifications

  1. Electrical System Procedure: Positioning of wire boxes → Conduit laying → Wire threading → Installation of distribution boxes → Installation of lighting fixtures → Installation of switches and sockets → Insulation testing.
  2. Overall Procedure: Pre-embedding of sleeves in prefabricated walls → Structural assembly → Surveying and setting out → Wall hole opening → Pipeline installation → Wire laying → Equipment installation → System testing → Completion acceptance.

III. Key Construction Techniques

  1. Wall Hole Opening

    • Use an infrared ray projector to mark the center point of the hole. For holes with a diameter > 80mm, drill four φ12mm stress relief holes. Use a diamond water drill for hole opening to minimize structural damage.
  2. Wire Conduit Pre-embedding

    • Preferably pre-embed pipelines in beams. When pre-embedding in floor slabs, place them between the upper and lower steel reinforcement meshes. The pipe diameter should not exceed 1/4 of the slab thickness; otherwise, add φb4 steel reinforcement meshes (width ≥ 240mm).
    • Avoid crossing more than two layers of pipelines in a three-dimensional manner. At the distribution points of multiple pipelines, arrange them in a radial pattern. Add Φ4@150 steel reinforcement meshes with a width of 500mm for parallel pipelines.
    • Securely fix pipe joints and wire box connections, and seal the pipeline openings with tape to prevent concrete infiltration.