The filling of wall joints in cement prefabricated houses should be carried out according to standardized procedures, with attention to material selection and safety considerations. The specific process and key points are as follows:

1. Clean the Joints
Before construction, thoroughly clean the wall joint area. Use a scraper or hard tool to remove loose debris, dust, and old filler from the joints, ensuring the edges of the joints are flat. If there is oil or moisture in the joints, wipe it with a dry cloth or dry it with a hairdryer to avoid affecting the adhesion of the filling material. Cleaning is the foundation for ensuring a good filling effect; if impurities remain in the joints, it may lead to material cracking or detachment.

2. Select the Filling Material
Choose the appropriate material based on the width and location of the wall joints:

  • Width < 3 cm: Preferably use plastic steel mud or plastic steel paste. These materials have good flexibility and can adapt to slight deformations, making them suitable for sealing small joints.
  • Width ≥ 3 cm: Use quick-drying cement, which hardens quickly and has high strength, effectively supporting the stress of larger joints.
  • Joints between walls and door/window frames: Fill directly with joint sealant or polyurethane foam. The former is suitable for dry environments, while the latter has both insulation and soundproofing functions.
    Materials should be purchased from legitimate channels, and their production dates and expiration dates should be checked to avoid using expired or inferior products.

3. Mix and Fill
Mix the material according to the product instructions (e.g., quick-drying cement needs to be mixed with water in a specific ratio). Use a small scraper, putty knife, or trowel to evenly fill the joint filler into the joints, ensuring it is fully compacted and free of voids. When filling, operate in layers, with each layer not exceeding 1 cm in thickness. Wait for the bottom layer to harden slightly before filling the next layer to reduce shrinkage cracks. For vertical joints, fill from the bottom up to prevent the material from sagging.

4. Post-Filling Treatment

  • Smooth the Surface: Use a trowel to scrape off excess joint filler around the joints, making it flush with the wall surface to ensure a neat appearance.
  • Wait for Hardening: Control the hardening time according to the type of material (e.g., quick-drying cement takes about 1-2 hours, while sealant takes 24 hours). Avoid touching or applying pressure during this period. Sanding or painting before complete hardening can cause the material to powder or detach.
  • Sanding Treatment: After the material has fully hardened, gently sand the filled area with sandpaper to make it blend smoothly with the wall, reducing color differences and tactile differences.

Safety and Structural Considerations

  • If the wall joint passes through beams and columns, is wider than 3 cm, and reaches the steel reinforcement in depth, it may involve structural damage. Stop construction immediately and contact a professional engineer to evaluate and repair the plan.
  • Wear gloves and a mask during construction to avoid skin contact or inhalation of dust; keep children away from the construction area to prevent accidental contact with unhardened materials.
  • Store filling materials according to the instructions to avoid performance degradation due to high temperatures or humidity.