The installation of box-group mobile toilets requires step-by-step standardized operations, covering preliminary planning, main body hoisting, system connection, and other aspects. The specific process is as follows:

I. Preliminary Planning and Preparation
- Demand Analysis and Site Selection Evaluation
- Estimate the pedestrian traffic volume and usage duration based on the usage scenario (such as scenic spots, construction sites, or temporary events), and select a flat area with solid soil and convenient drainage.
- Ensure that the selected site is far from open flames and flammable materials, avoids obstructing traffic, and takes into account the privacy and convenience of users.
- On-Site Survey and Foundation Treatment
- Accurately measure the site dimensions and check for underground obstacles (such as pipelines and tree roots) to avoid conflicts during subsequent construction.
- Pour a concrete platform or lay and compact graded gravel foundation according to the self-weight and load-bearing requirements of the toilet to ensure a level and long-term stable foundation.
- Equipment Inspection and Route Planning
- Open the package and check the completeness of the components, verify whether internal facilities such as sanitary ware, lighting, and ventilation fans are intact, and eliminate any transportation damage.
- Plan the transportation route, clear obstacles, and ensure sufficient hoisting space (such as the boom range of a crane).
II. Hoisting and Positioning of the Main Structure
- Safe Hoisting
- Use a crane or a large forklift operated by professionals to firmly attach the hoisting straps or steel cables to the dedicated hoisting points on the box.
- Slowly and steadily lift the box, avoiding violent shaking. On-site personnel should stay away from the hoisting area to prevent accidents.
- Precise Positioning
- Lower the box onto the foundation, adjust it to a completely fitted and level state, and use a level gauge for multi-angle calibration.
- For multi-unit combined toilets, hoist the modules in sequence according to the design drawings to ensure accurate docking positions and uniform gaps.
III. System Connection and Internal Integration
- Water Supply and Drainage System Connection
- Water supply connection: Connect to a clean water source through pre-buried pipeline interfaces using food-grade hoses or PPR pipes, and install valves and filters.
- Drainage and sewage discharge: Lay pipelines to the designated path (such as a septic tank or municipal sewage network), ensuring tight interfaces without leakage to avoid environmental pollution.
- Water and Electricity Connection
- Connect to the pre-designed water and electricity interfaces, which usually takes 1-2 hours and should be operated by a professional electrician to avoid short circuits or electric leakage risks.
IV. Other Precautions
- Load-Bearing Requirements: The ground load-bearing capacity should be ≥5 tons per square meter, and the load-bearing standard for transportation vehicles is usually 30-40 tons.
- Simplified Steps Reference: The installation of container-type mobile toilets can be simplified into foundation preparation (leveling the ground or a simple foundation), hoisting and placement (controlling the speed at 0.5-1 meter per second), and water and electricity connection.