The installation of container houses in Zhaodong City can be carried out according to the following steps:

Step 1: Determine the site and foundation
Choose a flat, dry, and well-drained site, avoiding low-lying or easily waterlogged areas. Before installation, clear the site of debris, garbage, and obstacles, and use measuring tools to determine the site dimensions to ensure they match the design specifications of the container house. The foundation type should be selected based on geological conditions and usage requirements:
- Steel foundation: Suitable for short-term use or temporary buildings, with a short construction period and low cost;
- Concrete foundation: Preferred for long-term use scenarios, requiring pre-pouring and curing to ensure adequate strength;
- Wooden foundation: Suitable for scenarios with stable geological conditions and low load requirements, requiring anti-corrosion treatment.
Foundation construction should ensure a levelness error of no more than 5 millimeters to avoid tilting or uneven structural loading during subsequent installation.
Step 2: Make on-site adjustments
Determine the installation direction (such as orientation and window/door positions) and layout (such as single-box or multi-box assembly) of the container house according to the design drawings. Use a level, laser distance meter, and other tools to check the foundation levelness and correct errors by adjusting the foundation height or using shims. At the same time, conduct a comprehensive inspection of the container box:
- Observe whether the box surface is smooth, without dents, rust, or cracks;
- Check whether pre-processing parts such as cutting and reinforcement meet design requirements;
- Confirm the structural integrity of the box to avoid deformation caused by transportation or handling.
Step 3: Erect columns and beams
Columns are the vertical load-bearing structures of the container house and should be fixed to the foundation at the designed spacing, usually using bolt connections or welding. During installation, ensure that the column verticality error does not exceed 3 millimeters and use temporary supports to prevent tipping. Beams, as horizontal load-bearing structures, should be precisely connected to the columns to form a stable frame system. This step requires a focus on checking the firmness of connection nodes to avoid structural instability caused by welding defects or loose bolts.
Step 4: Install the container
For single-box installation, use a crane or forklift to lift the container to above the foundation, slowly lower it to the predetermined position, and achieve precise connection by adjusting the foundation height or box angle. For multi-box assembly, install the bottom-layer containers first, then stack them layer by layer, and fix adjacent boxes using welding or bolt connections. Seal the joints to prevent rainwater leakage.
Step 5: Install roof and exterior wall facilities
Install附属 facilities (windows, doors, roof panels, skylights, and rainwater pipes) according to design requirements. Windows and doors should ensure smooth opening and closing and good sealing; roof panels should use waterproof materials, with slope design meeting drainage requirements; rainwater pipes should be aligned with the roof drainage outlets to avoid water accumulation. Additionally, insulation layers, soundproof layers, or decorative panels can be installed as needed to enhance house comfort.