The following information can be referred to for the installation of container houses in Yuxi:

I. Recommended Installation Manufacturers

Yuxi Zhongyue Integrated Housing Network Operation Center is a relatively well-known integrated housing manufacturer in the local area. It offers customization services for products such as integrated houses, quick-assembly container houses, packing-box units, movable panel houses, and container houses. Its service scope covers multiple regions in Yuxi, including Chengjiang, Eshan, Hongta, Huaning, Jiangchuan, Tonghai, Xinping, Yimen, and Yuanjiang. The manufacturer has the capabilities of steel structure research and development, processing and manufacturing, and plan implementation. It is equipped with a full set of standardized processing equipment and a complete quality control management process, and can provide one-stop services including plan design, production and processing, and delivery support.

II. Key Points of the Installation Process

  • Foundation Preparation: Installation should be carried out on a flat ground or workbench to ensure that the ground is solid and level, providing a stable foundation for subsequent installation.
  • Bottom Frame Installation: Connect the bottom corners of the container to the bottom beams using hexagon socket bolts, but do not tighten them temporarily. After adjusting to ensure that the diagonal difference of the bottom frame is ≤ 3mm, tighten the bolts.
  • Secondary Beam and Base Plate Installation: Install π-shaped secondary beams according to the positioning hole positions on the long beams and fix them. Lay the floor base plates along the 6-meter direction, and the base plates at both ends need to be cut at an angle according to the chalk line.
  • Floor Laying: Mark the center line of the π-shaped beams, start laying the floor from one end, making the joint coincide with the center line of the π-shaped beams. After laying, snap a chalk line and fix it with nails, with a nail spacing of 300 - 350mm.
  • Subsequent Treatment: Sand the entire floor, apply PVC special floor adhesive, wait for 10 - 15 minutes, then lay the floor covering and expel the air. If possible, perform welding treatment on the joints of the floor covering.

III. Installation of Special Types

The installation of foldable container mobile houses is relatively simple. With the operation of professionals, it can be completed in about three minutes with the cooperation of two people. During installation, first check the stability of the steel wire ropes, lift the main frame, unfold it, and place the support rods. Then push open the walls and tighten them with fastening screws. Finally, lift the foldable container house to the predetermined position and put it down.