Xinjiang hoisting prefabricated housing, represented by the new type of cement hoisting houses in the Circular Economy Demonstration Cluster in Tacheng City, is a modular building form that is quickly constructed through factory prefabrication and on-site hoisting.

I. Core Advantages
- Efficient Construction: It takes only half a day from hoisting to completion. After use by farmers and herdsmen, new house construction can be completed within a week, significantly shortening the traditional house-building cycle.
- Cost Optimization: In the mode of contracting for labor, materials, and including a cast-in-place roof, the cost per square meter is reduced by seven to eight hundred yuan compared to conventional house building. The materials used are commercial concrete and meet environmental protection standards.
- Quality Assurance: Through advanced processes and environmentally friendly materials, it achieves earthquake and wind resistance while also having energy-saving and environmental protection characteristics, providing a safe and comfortable space for occupants.
- Easy Operation: The modular design reduces construction difficulty, allowing ordinary farmers and herdsmen to complete the assembly independently. Tacheng Runchang Trading Co., Ltd. also provides technical support and after-sales service.
II. Key Installation Technologies
- Foundation Treatment: The site needs to be leveled and compacted, with soft soil layers and debris cleared away. If the bearing capacity is insufficient, qualified backfill soil should be replaced and compacted in layers. After foundation construction, sufficient curing is required. Before hoisting, positioning lines should be snapped and dimensions checked, and the top surface should be leveled.
- Module Hoisting and Alignment: Appropriate lifting equipment should be selected to ensure even force distribution. During lifting, keep it stable to avoid collisions. When lowering, align it with the positioning lines, adjust the verticality and levelness, and check the accuracy after each module is assembled in the case of multi-module assembly.
- Joint Gap Treatment: After cleaning the gaps, fill them with waterproof sealing mortar and smooth them out. After drying, apply waterproof sealing glue. When plastering the interior and exterior walls, lay alkali-resistant mesh cloth to prevent cracking.
- Node Reinforcement and Waterproofing: Reinforce the top nodes and vertical connection parts to ensure the overall structural stability and durability.
III. Enterprise Practices Tacheng Runchang Trading Co., Ltd. has improved production efficiency by introducing advanced equipment. In the first half of this year, it has produced more than 200 sets of cement products with a total area of over 3,000 square meters. It is expected to reach 6,000 square meters by the end of the year, and its products cover the needs of residents around Tacheng and urban construction.