Back to blog
Article

Cost of Prefabricated Houses in Shenzhen

Admin September 18, 2026

The comprehensive cost per cubic meter of prefabricated houses in Shenzhen is approximately 2019 yuan, with significant differences in cost per square meter for different structural types: light steel structures range from 1500 to 2500 yuan/㎡, wooden structures from 2000 to 3500 yuan/㎡, and concrete structures from 3000 to 4000 yuan/㎡.

Unit Cost Composition of Prefabricated Components

Taking a prefabricated building project in Shenzhen as an example, the cost composition is divided into the following seven categories:

  1. Factory Construction Amortization: The investment for self-building a 4000㎡ prefabrication factory is approximately 2 million yuan. After straight-line amortization over 5 years, the amortized cost per cubic meter of components is about 20 yuan; if mold amortization is included, the total amortized cost rises to 28 yuan/cubic meter.
  2. Raw Materials and Building Material Consumption: Concrete and steel bars are the main materials. The consumption of C30 concrete is 1.02 cubic meters per square meter, and the usage of steel bars is about 110 kg per cubic meter. The cost of auxiliary materials is approximately 50 yuan, resulting in a total material cost of about 1000 yuan per cubic meter.
  3. Freight and Logistics: The combined cost of transportation and lifting/loading/unloading is 100 yuan per cubic meter, significantly influenced by transportation distance and component volume.
  4. Labor Costs: Assuming workers work 8 hours a day, the average daily comprehensive cost is about 2500 yuan, with a unit labor cost of 100 yuan per cubic meter, directly related to production efficiency.
  5. Machinery and Energy: The rental cost for equipment such as overhead cranes and mixing stations is about 200,000 yuan per month. The cost of electricity for production is about 20 yuan per cubic meter, and the energy consumption of fuel-powered machinery is 30 yuan per cubic meter, totaling 250 yuan per cubic meter.
  6. Taxes and Management: The total taxes per cubic meter of concrete are approximately 338 yuan, and the management fee is 5% of the output value, i.e., 133 yuan per cubic meter, related to project scale and policies.
  7. Hidden Costs: Including tea money of 50 yuan and risk deposit of 20 yuan, totaling 70 yuan per cubic meter, usually related to project coordination and risk control.

Cost Differences Among Different Structural Types

The cost of prefabricated houses varies significantly due to differences in structural type, materials, and specifications:

  • Light Steel Structure: Mainly made of steel, with a short construction period, the cost per square meter ranges from 1500 to 2500 yuan, suitable for low-rise residential or temporary buildings.
  • Wooden Structure: Mainly made of wood, with good environmental performance, the cost per square meter ranges from 2000 to 3500 yuan, often used for villas or cultural and tourism projects.
  • Concrete Structure: Mainly composed of prefabricated concrete components, with strong earthquake resistance, the cost per square meter ranges from 3000 to 4000 yuan, suitable for high-rise residential or commercial buildings.

The actual cost needs to be comprehensively evaluated based on factors such as project scale, design complexity, and fluctuations in material market prices.