The compensation for the demolition of prefabricated concrete houses in Shenmu needs to be comprehensively determined based on the nature of the houses, the reasons for demolition, and local policies, and can be divided into the following three scenarios:

I. Compensation Scenario for Subsidence Caused by Coal Mine Goafs If a prefabricated concrete house is damaged due to subsidence caused by coal mining, it should be handled in accordance with the "Shenmu City Compensation, Relocation, and Resettlement Measures for Subsidence Caused by Coal Mine Goafs". The compensation principle is "who induces, who manages; who damages, who compensates and resettles". Compensation methods include land restoration, financial compensation, and resettlement. The specific process involves household registration surveys, house measurement and registration, negotiation of compensation fees, and signing of agreements, with an emphasis on the principle of "relocation before coal mining". This type of compensation is only applicable to scenarios requiring relocation and resettlement due to subsidence caused by goafs. It requires professional institutions to assess the degree of subsidence and house damage, and the compensation standards are related to the house structure, area, and depreciation rate.

II. Scenario of Houses Illegally Built in a Rush If a prefabricated concrete house is built in a rush after the issuance of the expropriation announcement (such as the "concrete maze" case in Xinhua Village, Shenmu), according to the "Regulations on the Expropriation of Houses on State-owned Land and Compensation" and relevant regulations in Shaanxi, such houses are not eligible for compensation. For example, Xiwan Coal Mine once explicitly denied the "2.2 billion compensation plan" and pointed out that rush-building behavior might lead to legal debts. The determination of illegal rush-building is based on the time of the expropriation announcement. The rush-built parts not only cannot obtain compensation but may also face forced demolition or administrative penalties.

III. Compensation Scenario for Legal House Demolition If a prefabricated concrete house is a legal building and meets the conditions for demolition, it can usually receive compensation, including compensation for the value of the house, relocation and resettlement subsidies, and compensation for losses due to production and business suspension. The compensation amount needs to be determined by an appraisal institution based on the house structure (such as prefabricated panels, brick-concrete, etc.), area, depreciation rate, and local policies. For example, in the house renovation project in Xigou Street, Shenmu City in 2025, legal rural houses were upgraded in quality through resin tile replacement and wall renovation, but no demolition compensation was involved, indicating that the compensation for legal houses is subject to actual demolition, and the compensation standards vary depending on the project type (such as renovation or expropriation).

Summary: The compensation for the demolition of prefabricated concrete houses in Shenmu requires strict differentiation of scenarios. Houses built illegally in a rush are not eligible for compensation; legal houses are compensated according to appraisal standards; and subsidence caused by goafs should be handled in accordance with special measures. It is recommended to verify the legality of the house, the reasons for demolition, and local policies before demolition, and safeguard rights and interests through legal means if necessary.