Rural Prefabricated House Construction Plan

Admin September 18, 2026

The construction of rural prefabricated houses requires comprehensive planning from aspects such as construction deployment, preparation, process, and advantages. The specific plan is as follows:

I. Overall Construction Deployment
Four core objectives need to be clarified:

  1. Quality Objectives: The strength of the foundation concrete should reach above C30. The verticality deviation of prefabricated component installation should be ≤3mm/m, and the surface flatness should be ≤5mm/2m. The excellent rate of key processes should be ≥95%, in line with the requirements of the 'Technical Specification for Assembled Concrete Structures'.
  2. Safety Objectives: Achieve 'zero deaths and zero serious injuries', with the minor injury frequency controlled within 3‰. The certificate-holding rate of special operation personnel should be 100%, and the compliance rate of temporary electricity use should be 100%.
  3. Progress Objectives: The total construction period is 120 days, including 45 days for prefabricated component production, 50 days for on-site installation, and 25 days for decoration. The critical path is foundation construction → main structure installation → roofing works → completion acceptance.
  4. Cost Objectives: The unit construction cost should be controlled within 1800 yuan/㎡. Through factory production, the material loss rate should be reduced to below 3%, and the mechanical utilization rate should be increased to above 85%.
    In terms of organizational structure, a project management department should be established, with five professional teams under it: technology, production, quality and safety, materials, and logistics. A daily briefing meeting system should also be established.

II. Construction Preparation Stage

  1. Drawing Review: Focus on reviewing the split dimensions of prefabricated components (wall panels ≤3.5m×6m, weight ≤8t), joint connection details (such as sleeve grouting and grout-anchored lap joint details), and the positions of reserved holes (coordinate deviation of pre-embedded water and electricity pipelines ≤5mm). Use BIM technology to complete clash detection, lifting path planning, and progress simulation.
  2. Site Preparation: After site leveling, the foundation bearing capacity should be ≥150kPa, and the drainage slope should be ≥2%. The width of temporary roads should be ≥4m (hardened with C20 concrete, thickness 150mm). Set up 1.2m-high strip foundations in the component stacking area, with wooden square pads arranged at 2m intervals. Build a 30㎡ rain-proof shed for the material warehouse and equip it with 4 sets of fire extinguishers. Set up 1.8m-high hard barriers in the lifting operation area and hang warning signs.
  3. Production Control: Use CNC stirrup benders for steel bar processing, with a dimensional deviation of ≤±5mm. For mold acceptance, the joint gap of steel molds should be ≤0.5mm, and the flatness should be ≤2mm/m. Use pump delivery for concrete pouring, with a vibration time of 30-45s per point. During factory inspection, ensure that the honeycomb area is ≤0.02% of the component surface area, there are no through cracks, and the dimensional deviations (length/width ±5mm, thickness ±3mm, diagonal difference ≤10mm). The compressive strength of test blocks cured under the same conditions should be ≥100% of the design value. Use special vehicles for transportation and set up fixing measures.

III. Main Construction Process (Taking a panel house as an example)

  1. Erecting the Steel Frame: Use steel structures to build a framed structure with a roof, taking 2-3 days.
  2. Building the Walls: Use 'Oriented Strand Board' (OSB) for the inner layer (to prevent deformation) and cover the outer layer with cement boards.
  3. Waterproofing Treatment: Apply waterproof coatings. It is recommended to apply multiple layers to ensure effectiveness.
  4. Exterior Wall Decoration: Install replaceable exterior wall decorative panels (such as white panels).
  5. Interior Decoration: Fill with thermal insulation cotton, use gypsum boards for the interior walls, and complete the construction of the basic panel house.

IV. Core Advantages of Prefabricated Houses
Taking a rural case in Henan as an example, the cost of a prefabricated house is only over 300 yuan per square meter, with a 70-year quality guarantee. Factory-standardized production of components is adopted, allowing for rapid on-site assembly, similar to a 'building block' model. The structure is made of reinforced concrete, providing high strength and stability, and can withstand external impacts and the test of the natural environment.