Relocation of Squat Toilet in Toilet Renovation
The relocation of the squat toilet in toilet renovation can be achieved through the following methods, and the appropriate plan should be selected based on the bathroom structure and requirements:

1. Remove the original squat toilet and re-lay the pipes If the bathroom has a sunken space or allows the floor to be raised, first break the original squat toilet, clean the base layer, and then re-plan the direction of the sewer pipes. Ensure that the slope of the new pipes meets the drainage requirements (usually 1%-3%) to avoid water accumulation or bad odors. After laying the pipes, level the floor with cement mortar, lay tiles, and finally install a new squat toilet. This method is suitable for long-distance relocation, but the construction period is relatively long and the cost is high. Attention should be paid to waterproofing to avoid damaging the original waterproof layer.
2. Use a side-discharge squat toilet (suitable for bathrooms without sunken spaces) If the bathroom has no sunken space and the position of the squat toilet needs to be moved, a side-discharge squat toilet can be selected. Its drainage outlet is on the side and is connected to the main drainage pipe through a horizontal pipe, but the following should be noted:
- Step issue: The side-discharge design may require raising the floor to form steps (about 15-20 centimeters high) after the squat toilet is installed, which affects user comfort, especially for the elderly or children.
- Space limitation: Ensure that the length of the horizontal pipe does not exceed the specified requirements (usually no more than 1.5 meters), otherwise it is prone to blockage. This plan is suitable for small-scale adjustments and scenarios that are not sensitive to the step height.
3. Refer to the toilet relocation method (short-distance adjustment) If only a slight adjustment of the position (10-40 centimeters) is required, the toilet relocation technology can be used for reference:
- Relocator: Install a special relocator to connect the original drainage outlet and the new squat toilet, but the distance must be strictly controlled (no more than 40 centimeters), otherwise the flushing force will be weakened and blockage is likely to occur. During construction, a slope (1%-3%) should be reserved to ensure smooth drainage.
- Raise the floor: By raising the entire bathroom floor (about 5-10 centimeters) and re-laying the pipes, more flexible position adjustments can be achieved. This method has a relatively low cost, but it will reduce the floor height, and the impact on the space needs to be evaluated. Note: After relocation, strengthen the waterproof test and regularly check the pipe seal.
Key construction points:
- Waterproofing: After any pipe changes, re-apply waterproof coating and conduct a 24-hour closed-water test.
- Slope control: Insufficient slope of the drainage pipes will lead to slow drainage, while an excessive slope may affect the stability of the squat toilet.
- Material selection: Give priority to PVC or cast iron pipes, and avoid using inferior materials that may cause leakage.
It is recommended to comprehensively evaluate the plan based on the actual structure, budget, and usage requirements of the bathroom, and consult a professional plumber or designer if necessary to ensure that the construction complies with regulations and can be used without worries in the long term.