The removal of container and prefabricated houses must follow standardized procedures to ensure safety and legality.

I. Preparation and Approval Before Removal
If the container house is an illegal structure (e.g., occupying public space without approval), cooperation with law enforcement agencies is required to complete rectification procedures. For example, in the Chedun Town case, the party responsible for the illegal structure received a notice of rectification within a specified period and was required to clear internal items and cooperate with assisted demolition. Before legal removal, it is essential to confirm property ownership and approval status to avoid legal risks.
II. Safe Dismantling Procedures
Personal Protection and Site Preparation
- Operators must wear protective equipment such as helmets, non-slip shoes, and gloves. For high-altitude work, safety harnesses must be worn, and stable scaffolding must be erected.
- Designate a restricted area on-site, keep unauthorized personnel away from the dismantling area, and have a dedicated person in charge of unified command with clear division of labor.
Electrical Facility Removal
- Cut off the main power supply: Turn off the main switch of the house, use a voltage tester to confirm no electricity, and then remove wires, switches, sockets, and distribution boxes.
- Component organization: Store electrical components by category to prevent damage or loss, facilitating subsequent recycling or disposal.
Structural Dismantling
- Removal of connectors: Use tools such as wrenches to apply even force and remove bolts and connectors between container bodies, avoiding violent dismantling that may cause deformation. Collected bolts must be stored uniformly to prevent loss.
- Layer-by-layer removal: For multi-story structures, removal must proceed from top to bottom. When using a crane for lifting, ensure the ropes are secure and the container body is stable, with no one allowed underneath. After lifting to the designated location, place it slowly to avoid collision.
Site Cleanup and Inspection
- After dismantling, clear debris and components, and store container bodies and materials by category to prevent rust or damage.
- Safety confirmation: Check the site for hidden hazards such as sharp objects or exposed wires, and confirm no risks before leaving.
III. Special Scenario Considerations
- Illegal structure handling: As in the Chedun Town case, cooperation with law enforcement agencies is required to complete filing, rectification, and assisted demolition procedures to avoid additional losses from forced demolition.
- Environmental protection requirements: Waste generated from dismantling must be sorted for disposal. Metal components can be recycled, and construction waste must be transported to designated locations to avoid environmental pollution.
The removal of container houses requires a balance between safety and compliance. Strictly following operational procedures ensures both personnel safety and avoidance of legal disputes and environmental risks.