Flowchart of Prefabricated Panel House Construction
Admin September 19, 2026
The construction process of prefabricated panel houses can be divided into four stages: design, component production, on-site construction, and post-construction. The specific processes and technical requirements are as follows:

I. Design Phase
- Structural Design: Determine the types of prefabricated components (such as prefabricated exterior wall panels, composite slabs, beams, stairs, etc.) based on building requirements and complete the overall structural design.
- BIM Detailed Design: Utilize BIM software for component disassembly design, clash detection, and process simulation to optimize the construction plan.
- Drawing Preparation: Prepare construction drawings and prefabricated panel layout diagrams, specifying panel numbers, specifications, installation sequences, and locations of reserved holes.
II. Component Production Phase
- Factory Prefabrication:
- Fabricate steel molds, bind reinforcement bars, and reserve lifting hooks and holes;
- Pour C30 concrete (e.g., for hollow slabs with a span of 3.6-4.2m, thickness of 150mm, and equipped with HRB400E grade reinforcement bars), and stack the components by category after demolding;
- Mark the finished products with component numbers, installation directions, and other information.
- Transportation and Arrival:
- Transport the components according to the arrival plan, using specialized frames to prevent damage;
- Inspect the appearance (no cracks or honeycombing), dimensional deviations (±5mm), and bearing capacity reports upon arrival. Installation can only proceed after passing the inspection.
III. On-site Construction Phase
- Foundation Construction:
- Complete the cast-in-place main structure of the basement, podium, and the first two floors above ground (e.g., using a prefabricated shear wall system);
- Verify the axis lines, elevations (allowable deviation ±5mm), and support flatness (≤5mm/2m) to ensure the installation accuracy of prefabricated panels.
- Prefabricated Component Hoisting:
- Exterior Wall Installation: Measure and set out lines → hoist wall panels → observe reserved reinforcement bars for alignment using a mirror → install diagonal supports to correct verticality → unhook;
- Prefabricated Panel Installation: Snap control lines → hoist panels in the order specified in the layout diagram → ensure the panel end resting length is ≥120mm → control the panel joint width between 20-50mm.
- Connection and Pouring:
- Bind reinforcement bars at connection points and pour concrete for nodes and the cast-in-place layer of beams and slabs;
- Seal the joints of prefabricated wall panels (using dry-hard cement mortar) and grout (block the grout pipes one by one) to ensure structural integrity.
IV. Post-construction Phase
- Waterproofing and Insulation:
- Lay 3mm thick SBS waterproof membranes and seal panel joints and eaves gutters;
- Install a 100mm thick extruded polystyrene board insulation layer and a 40mm thick C20 fine aggregate concrete protective layer.
- Scaffolding and Finishing:
- Use an integrated self-lifting scaffold from the third floor to enhance construction safety;
- Factory-produce interior finishes for rapid assembly and disassembly, shortening the construction period.
Key Technical Requirements:
- Plan the hoisting sequence reasonably (e.g., following the principle of 'exterior before interior, heavy before light') to minimize repeated operations;
- Use mobile terminals connected to the BIM platform to monitor component positions, installation progress, and quality data in real-time.