The installation of prefabricated houses should follow the following steps and key points:

I. Base Treatment
Before installing prefabricated components, the top surface of the load-bearing wall should be pre-treated. One day before lifting, the wall top should be fully moistened with water, but water accumulation should be avoided. High-grade cement mortar should be used to level the wall top, ensuring a flat surface and uniform mortar laying. After placing the prefabricated panels, the mortar will be compacted, forming a 'face-to-face' structure that enhances the connection stability between the panels and the wall.

II. Panel Bottom Support and Panel Joint Treatment

  1. Support Setting: During the installation of prefabricated panels and concrete pouring, temporary supports should be set at the bottom of the panels to prevent bending or cracking due to incomplete component strength formation. The supports should be stable and evenly distributed to ensure safe load transfer.
  2. Panel Joint Treatment: The joints between adjacent prefabricated panels should be strictly treated to avoid future leakage. Sealing materials can be used for filling or grout injection spaces can be reserved to ensure joint tightness.

III. Prefabricated Column Installation
Install in the order of 'foot columns → side columns → central columns', using the axis and outer contour lines as control references. Side and corner columns should be aligned with the outer contour lines to ensure overall structural verticality and positional accuracy. During installation, a theodolite or total station should be used for real-time verification.

IV. Prefabricated Shear Wall Installation

  1. Lifting Sequence: Follow the principle of 'exterior walls first', prioritizing the installation of wall panels connected to the cast-in-place sections.
  2. Control Line Setting: Exterior walls should be controlled by both the axis and contour lines, while interior walls should be primarily controlled by the axis.
  3. Compartmental Grouting: For wall panels requiring compartmentalization, use bedding mortar for compartmentalization. The thickness of grouting material laid for multi-story shear walls should not exceed 20mm to ensure grouting density.

V. Installation of Prefabricated Beams, Composite Slabs, and Composite Beams

  1. Installation Sequence: Install main beams first, followed by secondary beams, and from low to high to avoid interference from cross-operations.
  2. Composite Slab Verification: After lifting, check the height difference and width of the panel bottom joints. If the height difference does not meet requirements, re-lift and adjust, using adjustable supports to precisely control the elevation.
  3. Support Removal: Temporary supports should not be removed until the strength of the post-poured concrete meets design requirements to prevent structural deformation.

Key Precautions:

  • All component installations should be based on control lines, using laser leveling instruments and other tools to ensure accuracy.
  • Grouting, bedding, and other materials should be mixed according to design ratios to avoid insufficient strength.
  • Key data (such as support spacing, grouting thickness) should be recorded during installation for quality traceability.