Panjin Container House Installation
The installation of container houses in Panjin requires following a professional process, covering foundation preparation, structural assembly, plumbing and electrical installation, and decoration, with an emphasis on measurement accuracy, node connections, and safety standards.

1. Foundation Preparation and Measurement
Before installation, ensure the ground is level. Verify foundation dimensions against design drawings, with axis deviations controlled within ±25mm and wall height deviations not exceeding 10mm. For concrete foundations, reserve anchor bolt holes; for brick foundations, construct in advance and reserve connector positions. After foundation completion, perform level calibration to ensure stability of the container base frame.
2. Structural Assembly and Connection
- Base Frame Installation: Connect container corners to base beams using hex bolts, temporarily leaving them loose; adjust diagonal differences of the base frame to ≤3mm before tightening bolts.
- Secondary Beam and Floor Installation: Install π-shaped secondary beams according to long beam positioning holes and secure with self-tapping screws; lay floor substrates along the 6-meter direction, cutting corners at joints and snapping chalk lines, securing with cross-head flat燕尾丝 (replace with appropriate English term, e.g., 'flat-head screws'), with nail spacing of 300-350mm.
- Wall and Roof Installation: When assembling steel structures, secure square tube columns to steel beams with screws, checking for verticality and straightness; reserve door and window positions during wall panel installation and perform waterproofing after roof panel installation.
3. Plumbing and Electrical Installation and Concealed Works
- Pipe and Wire Embedding: Embed plumbing and electrical lines according to design drawings, ensuring accurate interface positions; electrical lines must be protected by conduits to prevent direct exposure.
- Waterproofing and Moisture Prevention: Focus on treating floor joints and connections between wall and roof panels, using PVC-specific floor adhesive and moisture-proof materials; seal doors and windows after installation to prevent leakage.
4. Decoration and Final Inspection
- Interior Decoration: After completing PVC ceiling panels and floor adhesive铺设 (replace with 'installation'), install doors, windows, and stair handrails; stair treads must use steel plates or angle iron for strength.
- Safety Inspection: Check bolt tightness, welding quality, and waterproofing effects; conduct load tests to ensure structural stability.
- Handover for Use: Notify the client for final inspection, confirming compliance with design requirements and safety standards before handover.
During installation, strictly adhere to the 'Technical Standard for Modular Container Houses' and the 'Quality Acceptance Specification for Steel Structure Construction' to ensure construction quality and safety.