When installing pipes for mobile toilets, it is necessary to comprehensively consider factors such as location selection, connection methods, sealing treatments, slope design, material selection, and construction acceptance to ensure smooth drainage and compliance with hygiene standards.

Location Selection and Basic Requirements
Before installation, choose a well-ventilated and easily drained site, ensuring sufficient operating space around the sewer outlet. For scenarios involving the rental of portable toilets, it is essential to survey the distribution of underground pipelines in advance, avoiding obstacles and preventing conflicts during later construction. Buried pipes should have a depth of no less than 30 cm to prevent freezing in winter or damage from human activities.Pipe Connection and Sealing Treatment
- Interface Adaptation: Precisely align the sewer pipe with the sewage outlet of the mobile toilet, selecting appropriately sized interfaces (such as rubber seals or specialized connectors) to avoid leakage caused by mismatched sizes.
- Sealing Enhancement: Apply a uniform layer of corrosion-resistant sealant at the connection points to ensure complete closure. For buried pipes, wrap the interfaces with waterproof tape or heat-shrink sleeves for double protection against moisture infiltration from the soil.
- Extension Direction: The other end of the sewer pipe should extend horizontally along the ground to the drainage point (such as municipal sewers or septic tanks), avoiding vertical drops that could cause splashing of sewage or the spread of odors.
- Slope Design and Pipe Diameter Selection
- Pipe Diameter Standards: For a single toilet unit, the main pipe diameter is recommended to be no less than 110 mm, and the branch pipe diameter no less than 50 mm. If the number of users exceeds 50, calculate the septic tank capacity based on a flow rate of 0.1 cubic meters per person per day and increase the pipe diameter accordingly.
- Slope Control: The pipe slope should be maintained between 3% and 5% to ensure self-flowing drainage of sewage. In low-lying areas, additional drainage wells can be installed or the slope increased to 8% to prevent water accumulation and blockages. If connecting to municipal sewers, confirm the elevation of the sewer network to avoid backflow.
- Material Selection and Construction Specifications
- Material Preference: It is recommended to use UPVC pipes or PE pipes, which are corrosion-resistant, aging-resistant, and have smooth inner walls that are less prone to scaling. Avoid using galvanized steel pipes and other easily rusting metal pipes to reduce maintenance costs in the later stages.
- Construction Methods: For exposed pipes, fix supports to prevent deformation; for buried pipes, use sand and gravel for backfilling to avoid damage from sharp stones. Use 45° elbows at pipe bends to reduce water flow resistance.
- Acceptance and Maintenance Points
After construction, conduct a water flow test by continuously injecting water for more than 30 minutes to check for leaks at the connections and ensure smooth drainage. During daily use, clean the sewer pipes monthly using professional tools (such as pipe cleaners) or manually to prevent the accumulation of grease and debris. If connected to a temporary septic tank, regularly pump out the feces to avoid overflow and environmental pollution.