The installation of drainage pipes for mobile toilets should follow the following steps and specifications:

I. Basic Conditions and Planning
The sewage pipes should be installed in areas with lower terrain and less prone to water accumulation to avoid long-term waterlogging that could cause pipe deformation or damage. It is recommended that the diameter of the main pipe be no less than 110mm and that of the branch pipes be no less than 75mm to ensure drainage efficiency. Determine the drainage path based on the layout of the mobile toilet. When planning, ensure that the pipes have a drainage slope of 2%-5% (i.e., a drop of 2-5 cm per meter) to allow sewage to flow naturally and prevent blockages.
II. Material and Tool Preparation
Select materials that are corrosion-resistant and have good compressive properties, such as PVC pipes or HDPE pipes, to adapt to outdoor environments. Prepare pipe fittings (elbows, tees, straight connectors, etc.), PVC-specific adhesive, measuring tapes, hand saws or pipe cutters, sandpaper or scrapers, and other tools. The quality of the materials directly affects the service life of the pipes, so choose qualified products that meet national standards.
III. Measurement and Cutting
Use a measuring tape to accurately measure the pipe length, mark it, and then cut it, ensuring that the cut is even. Use sandpaper to smooth the burrs inside and outside the pipe ends to avoid scratching the seals or causing leaks during connection. Reserve a certain margin when cutting to prevent the pipes from being too short due to measurement errors.
IV. Pipe Connection and Installation
Apply special adhesive to the spigot of the pipe and the socket of the fitting, quickly insert and rotate 90 degrees, and hold under pressure for a dozen seconds to initially secure. Fix the main pipe along the planned path using pipe clamps or expansion bolts, and check again to ensure the slope meets the requirements. The pipe burial depth should generally be no less than 500mm to prevent freezing and cracking; drainage wells or lifting devices should be installed in low-lying areas or at the end to ensure smooth drainage.
V. Branch Pipe and Sanitary Fixture Connection
Connect branch pipes using tees and other fittings according to the positions of the toilet, sink, etc. Apply adhesive to all connections and tighten them. The toilet is connected via a flange ring, while the sink and floor drain are connected using hoses or PVC pipes, with rubber gaskets and pipe clamps added at the connections to enhance sealing. After connection, check that all connections are secure to avoid leaks caused by loosening.
VI. Connection to Municipal Sewer Network
Prioritize connection to the municipal sewage network. If this is not possible, set up temporary sewage treatment facilities and discharge only after treatment meets standards. Before connection, communicate with the local drainage department and complete the necessary procedures to ensure compliance with environmental protection requirements.
VII. Inspection and Testing
After installation, visually inspect the connections and pipes for deformation and conduct a water flow test to ensure there are no leaks. Regularly inspect for blockages and leaks on a daily basis, and focus on checking drainage capacity before the rainy season, promptly clearing debris to ensure the normal operation of the system.