Reconstruction of Prefabricated Houses in Mingshui County

Admin September 18, 2026

The reconstruction project of prefabricated houses in Hexie Jiayuan Community, Mingshui County, has achieved phased progress and is expected to be completed and handed over by the end of 2024. Here is a detailed overview of the information:

I. Project Background and Accident Causes
As a shantytown renovation project in Mingshui County, Hexie Jiayuan Community was completed in 2010. In July 2019, after being appraised by a professional institution, the community was classified as a D-grade dangerous building, clearly identified as an engineering quality accident. Such dangerous buildings pose severe structural safety hazards and can no longer meet the requirements for safe living, necessitating immediate demolition and reconstruction measures. After the accident, relevant departments initiated a responsibility investigation process. The discipline inspection and supervision commission held 25 individuals accountable, and six suspects涉嫌犯罪 (suspected of criminal offenses) were prosecuted according to law, highlighting the government's zero-tolerance attitude towards engineering quality issues.

II. Reconstruction Progress and Timeline

  1. Demolition Phase: In December 2023, the demolition of the dangerous buildings officially commenced, clearing space for subsequent reconstruction.
  2. Reconstruction Initiation: In April 2024, the reconstruction project officially began, with a state-owned enterprise in the city responsible for implementation, ensuring the standardization and professionalism of project management.
  3. Main Structure Completion: In August 2024, the reconstruction project completed the封顶 (topping-out) of the main structure, marking the project's entry into the stage of interior decoration and supporting facility construction.
  4. Relocation and Handover: In December 2024, residents will begin relocating, and the project is expected to be fully completed and handed over by the end of the year, progressing efficiently ahead of the original schedule.

III. Quality Control and Responsibility Implementation
During the reconstruction process, the construction unit strictly adhered to construction procedures, strengthening quality supervision in all aspects from design and construction to acceptance, ensuring that the newly built houses meet national safety standards. Meanwhile, the government reinforced the responsibility chain through an accountability mechanism, preventing similar engineering quality accidents from recurring at the source and effectively safeguarding residents' lives and property.

IV. Social Significance and Livelihood Protection
By demolishing dangerous buildings and reconstructing safe housing, this project effectively resolved the living safety hazards of the original residents, serving as an important practice by the local government in implementing livelihood projects and enhancing urban safety levels. The reconstructed houses are expected to be equipped with complete infrastructure, further improving residents' living conditions and reflecting the government's continuous investment and determination in shantytown renovation and dangerous building management.