Jingmen Intelligent Mobile Toilet Installation

Admin September 27, 2026

The installation of intelligent mobile toilets in Jingmen should be standardized from three aspects: construction preparation, process flow, and key technical points.

I. Construction Preparation

  1. Technical Preparation: Organize technicians to familiarize themselves with design drawings, focusing on verifying foundation dimensions, equipment installation positions, and pipeline routes to ensure alignment with on-site conditions. Develop a specialized construction plan, specifying technical points for each process and quality control standards, and implement it after approval by the supervisor. Conduct hierarchical briefings for construction teams, covering construction procedures, process standards, safety regulations, and acceptance requirements.
  2. Material Preparation:
    • Main materials include light steel structure frames (Q235B steel, galvanized surface treatment), composite wall panels (50mm thick color steel plates, fire rating B1), anti-slip floor tiles (300×300mm, wear resistance coefficient ≥0.6), water supply and drainage pipes (UPVC φ50/φ110mm), and electrical cables (BV-2.5/4mm², insulation rating ≥750V).
    • Materials entering the site must be accompanied by factory certificates and inspection reports, and undergo visual quality inspections (e.g., deformation, damage, rust). Non-compliant materials are strictly prohibited from use.
  3. Equipment Preparation: Equip with measuring tools (level gauges, total stations, tape measures, spirit levels), installation tools (electric drills, angle grinders, hot melt welders), and safety equipment (safety helmets, fire extinguishers) to ensure construction efficiency and safety.

II. Construction Process Flow
Execute the following steps in sequence: Foundation construction → Main frame installation → Wall panel and roof installation → Floor laying → Water supply and drainage system installation → Electrical system installation → Ventilation equipment installation → Interior decoration → Cleaning and debugging. Each step must be closely linked to avoid rework.

III. Key Construction Technical Points

  1. Foundation Construction:
    • Site leveling requires clearing weeds and gravel, compacting with a road roller to ≥90%, with a flatness error ≤5mm/2m. Excavate foundation pits according to design dimensions (depth 500mm, slope ratio 1:0.5), and lay a 100mm thick graded gravel cushion at the base, compacted in layers.
    • Pour a C25 concrete foundation (3.2m×2.6m×0.3m), reinforced with φ10mm steel mesh (spacing 200mm×200mm), with embedded connectors on the surface.
  2. Main Body and System Installation: The main frame, wall panels, and roof must be fixed according to design requirements to ensure structural stability. The water supply and drainage system must undergo sealing tests, the electrical system must undergo insulation tests, and the ventilation equipment must undergo air volume debugging. Finally, complete interior decoration and cleaning debugging to ensure normal functionality.

Note: Some mobile toilet rental companies in Jingmen offer free installation services, suitable for temporary event scenarios, simplifying user operation procedures.