The installation of mobile toilets in Huzhou requires different processes based on their types, mainly divided into municipal mobile toilets and double-unit mobile toilets. The specific installation points are as follows:

Municipal Mobile Toilet Installation Process

  1. Pre-deployment Requirement Assessment

    • Environmental Survey: Conduct on-site inspections of the installation location, focusing on analyzing ground bearing capacity (e.g., reinforcement needed for soft soil foundations), drainage interface distance (prioritize areas adjacent to municipal sewer networks), power connection conditions (whether temporary power supply is required), and pedestrian flow lines (avoid affecting traffic efficiency).
    • Comprehensive Data Analysis: Determine equipment adaptability by considering Huzhou's climatic characteristics (e.g., drainage needs during the rainy season) and site usage (e.g., scenic spots, construction sites, or event venues).
  2. Equipment Selection

    • Technical Type Selection:
      • Flush Toilets: Suitable for areas in Huzhou with abundant water resources and well-developed municipal sewer networks, enabling sewage discharge through temporary pipe connections.
      • Vacuum Suction or Recirculating Flush Toilets: Used in venues lacking drainage facilities (e.g., temporary areas for large events), equipped with large storage containers for periodic removal of waste by specialized vehicles.
    • Parameter Configuration: Consider the number of toilet stalls (calculated based on pedestrian flow), accessibility features (e.g., ramps, handrails), material durability (corrosion resistance, fire rating ≥ B1), and wind and earthquake resistance (especially for mountainous areas or high-rise platforms).
  3. Installation Process

    • Foundation Treatment: Use concrete prefabricated panels or steel structural platforms for reinforcement to ensure long-term stability of the equipment and avoid settlement risks.
    • Pipe Connection: Connect water, electricity, and sewage pipes using specialized quick-connect technology and conduct leak tests (pressure ≥ 0.3 MPa, hold for 30 minutes without leakage).
    • Functional Debugging: For container-type toilets, inspect internal piping (e.g., flush systems, ventilation ducts) and ventilation systems (air exchange rate ≥ 8 times/hour) to ensure normal operation.
  4. Lease Model Management

    • The contract should clearly define the scope of services, including installation, routine maintenance (e.g., consumable replenishment, cleaning), troubleshooting, and removal, waste removal, and site restoration upon lease expiration.

Double-Unit Mobile Toilet Installation Process

  1. Purchase and Customization Services

    • Size Selection: The standard size is 2.4 meters in length × 1.5 meters in width, adjustable based on site size (e.g., narrow alleys or open squares) and pedestrian flow (e.g., demand during peak hours in scenic spots).
    • Appearance Customization: Supports color and logo customization (e.g., corporate logos or scenic spot theme colors), complying with visual standards in the Urban Public Toilet Design Standard (CJJ 14-2016).
  2. Installation and Acceptance

    • Site Acceptance: The installation team should complete setup within 3-5 working days, focusing on checking ground flatness (error ≤ 5 mm) and drainage slope (≥ 2%).
    • Hygiene Standards: Must comply with the Public Toilet Hygiene Standard (GB/T 17217-2021), including odor concentration (≤ 10 dimensionless), bacterial count (≤ 50 CFU/m³), and other indicators.

Common Requirements for Both Types of Toilets: Both must pass acceptance by environmental protection authorities after installation and undergo regular safety inspections (e.g., electrical insulation tests, structural stability assessments) to ensure long-term safe use.