How to Move the Position of a Squat Toilet
Moving the position of a squat toilet can be achieved by knocking out the original squat toilet and repaving, using a toilet offset connector, or selecting a plan based on the drainage method, depending on the actual situation.

I. Knocking Out the Original Squat Toilet and Repaving
If a large-scale relocation of the squat toilet is required, the most direct method is to knock out the original squat toilet, re-plan the drainage pipes, and lay new floor tiles. During construction, first turn off the water supply, remove the old squat toilet and surrounding floor tiles, clean the base layer, and then reconnect the sewer pipes, ensuring that the pipe slope meets the drainage requirements (usually 1%-3%) to avoid water accumulation or bad odors. After the pipes are laid, level the ground with cement mortar, lay new floor tiles, and finally install a new squat toilet. This method involves significant changes but can thoroughly solve the position problem and is suitable for same-floor drainage or when space allows.
II. Using a Toilet Offset Connector (for small-scale, short-distance relocation)
If only a relocation of 10-30 centimeters (no more than 40 centimeters) is needed, a dedicated toilet offset connector can be used. During construction, pay attention to the following:
- Slope reservation: A slope of 1%-3% should be reserved at the connection between the offset connector and the original drainage pipe to ensure smooth drainage;
- Installation height: After installation, the offset connector should be basically flush with the ground to avoid affecting the flushing effect or increasing the risk of blockage;
- Material selection: Prioritize PVC or ABS offset connectors, which are corrosion-resistant and have good sealing properties.
This method is low-cost and quick to construct but is only suitable for small-scale adjustments and may increase the probability of blockage with long-term use.
III. Selecting a Plan Based on the Drainage Method
- Same-floor drainage: If the bathroom has same-floor drainage (the drainage pipes are on the floor of the same level), the position of the drainage pipes can be directly changed without damaging the structure of the floor below, allowing for flexible changes at a relatively low cost.
- Inter-floor drainage: If it is inter-floor drainage (the drainage pipes are on the ceiling of the floor below), the following options should be selected based on the actual situation:
- Wall-mounted drainage: If the new position is close to the main pipe, a wall-mounted squat toilet can be used to reduce changes to the floor;
- Raising the floor: Hide the offset pipes by raising the entire bathroom floor (about 10-15 centimeters), but this will sacrifice ceiling height;
- Re-drilling and relocating: Obtain the consent of the owner of the floor below, drill a hole in the floor slab, re-lay the pipes, and perform formwork and waterproofing treatment. This method is costly but provides stable results.
Precautions: When relocating a squat toilet, strictly follow construction specifications, especially regarding drainage slope and waterproofing. If possible, prioritize same-floor drainage or re-drilling and relocating to reduce the risk of blockage in the later stage. It is advisable to consult a professional plumber before construction to ensure the feasibility of the plan.