I. Roof Insulation Layer Production

  1. Laying of Prefabricated Insulation Bricks

    • Applicable Scenarios: Top floors of commercial housing or rooftops of self-built houses by residents.
    • Construction Process:
      • Prefabrication and Curing of Insulation Bricks: Fabricate insulation bricks according to design dimensions and cure them until the strength meets the standard.
      • Roof Layout: Mark the laying positions to ensure the base layer is flat and firm.
      • Construction of Brick Piers for the Elevated Layer: Build brick piers on the roof to form an elevated layer (height adjusted according to design).
      • Laying of Reinforced Concrete Insulation Boards: Place the prefabricated boards on the brick piers and fill the gaps after the surface is dry.
    • Key Points: The base layer must be dry and crack-free, and the gap-filling material must be waterproof.
  2. Construction of Prefabricated Cement Insulation Boards on the Roof

    • Material Requirements: Use C20 strength grade concrete with a board thickness of 30mm and built-in steel wire mesh for reinforcement.
    • Construction Steps:
      • Base Layer Treatment: Clean the roof, repair cracks, and level it.
      • Construction of Supports: Build supports at a height of 200mm to form an air circulation layer.
      • Laying of Isolation Layer: Lay waterproof rolls or plastic films on the supports.
      • Laying of Insulation Boards: Install the insulation boards one by one with uniform gaps between them.
      • Gap Treatment: Seal the gaps with sealant and reserve deformation space at expansion joints.

II. Construction Process of Prefabricated Insulation Boards

  1. Preparation
    • Clean the construction area, remove debris, and determine the laying positions and directions according to the design drawings.
  2. Base Layer Treatment
    • Ensure the base layer is flat (error ≤ 3mm/2m), dry (moisture content ≤ 8%), and repair cracks with cement mortar.
  3. Laying of Insulation Boards
    • Lay the boards one by one according to the plan, control the gaps between boards at 3-5mm, and fix them with special adhesives or fasteners (such as expansion bolts).
  4. Gap Treatment
    • Fill the gaps with polyurethane foam or silicone sealant to prevent air infiltration from affecting the insulation effect.
  5. Inspection and Acceptance
    • Check the flatness (using a 2m leveling ruler), fixation firmness, and gap sealing to ensure compliance with design specifications.

III. Personal Experience Supplement (Installation of Insulation Cotton)

  • Material Selection: Use gypsum fiberboard as a workbench and reserve a margin of 0.5-1cm when cutting insulation cotton.
  • Installation Skills: Embed the insulation cotton into the gaps and press it lightly to fix it. Avoid excessive squeezing that may cause deformation and ensure tight fitting with the insulation boards.