I. Material and Tool Preparation

  1. Roofing Materials: Choose based on climatic conditions. In rainy areas, prioritize materials with strong waterproofing properties, such as color-coated steel sheets (thickness 0.4-0.6mm), PVC waterproof membranes, or fiberglass-reinforced plastic.
  2. Frame Structure: Use light steel keels or aluminum alloy brackets that meet load-bearing requirements (≥50kg/m²) to ensure structural stability.
  3. Tool List: Electric drill, self-tapping screws (length ≥30mm), polyurethane sealant, spirit level, safety harness, expansion bolts, etc.

II. Frame Installation and Fixation

  1. Dimension Measurement: Accurately measure the roof dimensions to ensure a 5cm overlap area between the frame and the wall, preventing rainwater from seeping through gaps.
  2. Main Beam Fixation: Secure the main beams to the wall using expansion bolts, with a bolt spacing of ≤80cm to ensure even longitudinal load-bearing.
  3. Secondary Beam Installation: Install secondary beams horizontally with a spacing of ≤50cm. Reinforce the intersections with the main beams using screws to form a grid-like structure, enhancing overall stability.
  4. Level Calibration: Use a spirit level to check the flatness of the frame, avoiding uneven stress on the panels or water accumulation due to tilting.

III. Roof Panel Laying

  1. Laying Direction: Lay the panels from low to high, utilizing gravity to guide rainwater naturally downward and reduce the risk of water accumulation.
  2. Overlapping Treatment: Ensure an overlapping width of ≥10cm between panels. Apply sealant evenly along the seams (approximately 200g per linear meter) to ensure water tightness.
  3. Screw Fixation: Space self-tapping screws at ≤20cm intervals, keeping them ≥3cm away from the panel edges to prevent cracking due to edge stress concentration.
  4. Solar System Reservation: If equipped with solar lighting, reserve cable channels on the roof and ensure proper insulation to prevent short circuits or electrical leaks.

IV. Waterproofing and Drainage Design

  1. Slope Control: Recommend a single-sided roof slope of 5°-10° to ensure rapid rainwater drainage and prevent material corrosion from water accumulation.
  2. Seam Reinforcement: Apply waterproof tape to all panel seams, with an edge turnover height of ≥15cm to form a double waterproof barrier.
  3. Sealing Strip Installation: Install sealing strips at panel seams to further block rainwater penetration paths.

Precautions: Wear a safety harness during installation to ensure safety during high-altitude work. After construction, check that all screws are tightened and the sealant is evenly applied to avoid details that may lead to water leakage.