The excavation of a drainage pool (septic tank) for mobile toilets should be carried out according to standardized procedures, as detailed below:

1. Confirm the Installation Location
Choose an area with higher elevation and smooth drainage. Ensure that the drainage pool is approximately 1.5 meters away from the main body of the mobile toilet to prevent pipe blockages or water accumulation due to excessive proximity. Additionally, avoid low-lying areas to prevent rainwater backflow or soil settlement that could affect stability.
2. Excavate the Foundation Pit
- Size Control: Determine the excavation depth based on the model of the mobile toilet, typically around 1.2 meters. The diameter should be 20 centimeters larger than the main body of the septic tank to provide space for subsequent leak-proofing and pipe connections.
- Pit Wall Treatment: The pit walls should be vertical and smooth to prevent instability during septic tank installation. After tamping the bottom, lay a 10-centimeter-thick layer of sand and gravel (or crushed stone with concrete leveling) to enhance the foundation's load-bearing capacity and prevent leakage.
3. Horizontal Positioning and Leak-Proofing
- Horizontal Calibration: Use a level to adjust the height of the septic tank's inlet and outlet to ensure they are at the same level as the ground drainage pipes, preventing drainage issues or backflow due to height differences.
- Leak-Proofing Measures: The pit walls and bottom should be treated for waterproofing. This can be done by applying a cement mortar finish (2-3 centimeters thick) or laying a PE waterproof membrane, ensuring there are no cracks or holes to prevent soil contamination from sewage leakage.
4. Pipe Connection and Odor Prevention
- Sealing and Fixing: Align the PVC drainage pipes with the septic tank's inlet and outlet, seal the interfaces with sealing rings, and then fix them with specialized adhesive to prevent pipe loosening or leakage.
- Anti-Backflow Design: Install an anti-backflow valve at the pipe connections to prevent odors or sewage from the septic tank from flowing back, enhancing the user experience.
5. Backfilling and Commissioning
- Layered Backfilling: First, backfill sand and gravel up to 5 centimeters above the pipes, then tamp the soil in layers (each layer not exceeding 20 centimeters thick) to prevent the septic tank from shifting or being damaged due to soil settlement.
- Function Testing: Open the inlet valve to check for smooth drainage and observe the septic tank and pipe connections for any leaks. If issues are found, repair them promptly and retest.
6. Safety and Maintenance
- Cover Design: Use precast concrete slabs (8-10 centimeters thick) or brick covers, leaving a 30-40 centimeter diameter opening for cleaning and securing it with a lock to prevent people from falling in or animals from entering. The cover should be 5-10 centimeters above ground level to prevent rainwater from entering.
- Regular Inspections: Check the pipe sealability quarterly and wrap insulation cotton around the pipes in winter to prevent freezing and cracking. Ensure the septic tank complies with local environmental emission standards and contact a professional company for cleaning and maintenance when necessary.
Tip: If technical difficulties arise during the operation (such as complex geology or poor drainage), it is advisable to contact a mobile toilet rental company or a professional construction team for assistance to ensure safety and compliance.