Back to blog
Article

How to Design Container Houses

Admin September 15, 2026

The design of container houses requires comprehensive consideration of structure, space, materials, lighting, insulation, and compliance. Here are the specific design points:

I. Structural Design Container houses take standard containers as the basic units. The main frame is mostly welded with hot-dip galvanized square steel (such as 100×100mm or 80×80mm specifications) to ensure stability and corrosion resistance. The design should comply with the Building Structural Design Code and adjust the frame strength according to the usage scenario. For example, in earthquake-prone areas, the seismic structure needs to be strengthened, and in areas with strong winds, the wind-resistant design should be optimized. Space expansion can be achieved through horizontal splicing, vertical stacking, or staggered-floor design. For example, double-wing expanded container houses can increase the usable area by 30%-50%, meeting the needs of temporary exhibitions or emergency rescue scenarios.

II. Spatial Layout and Functional Zoning

  1. Modular Combination: The conventional size of a single container for domestic trade is 3 meters × 6 meters, and for foreign trade, the size ranges from 5.8 meters × 2.2 meters to 11.5 meters × 2.2 meters. Through splicing and combination, flat-floor layouts such as integrated living and dining rooms, double bedrooms, and bathrooms with bathtubs (about 100㎡) can be formed, or staggered-floor designs can be used to create rich spatial levels, with the bottom floor reserved for leisure courtyards or aisles.
  2. Multi-functional Furniture Adaptation: For small units (such as 15㎡), it is recommended to use folding beds, folding tables, and integrated cabinets to enhance space flexibility. For example, the “Bamboo Whisper Mountain Retreat” project in Moganshan, Zhejiang, expands a single container into a 60㎡ LOFT space with a bedroom, living room, and observation deck through box cantilevering and hydraulic telescopic structures.

III. Material Selection and Weather Resistance

  1. Walls and Roofs: A composite sandwich panel structure is used, with an outer layer of aluminum-zinc color-coated steel plate, an intermediate layer filled with rock wool, glass wool, or polyurethane insulation material, and an inner layer that can be selected according to needs, such as bamboo and wood veneer, cement fiberboard, or metal brushed materials. For example, products for Hokkaido, Japan, are sprayed with a high-density polyurethane insulation layer on the walls, combined with a floor heating and air-conditioning dual heating system, achieving an ultra-low-energy building standard (K value ≤ 0.28W/㎡·K).
  2. Doors, Windows, and Glass: Insulated tempered glass is used to increase heat insulation and safety. The areas around doors and windows need to be sealed to prevent condensation. The roof can be designed with skylights or eaves sunshades to improve ventilation and lighting and enrich the facade appearance.

IV. Lighting and Insulation Design

  1. Lighting Optimization: By installing large floor-to-ceiling windows, roof skylights, or glass partitions, the indoor brightness can be improved. For example, the “Bamboo Whisper Mountain Retreat” project uses a full floor-to-ceiling glass wall to integrate the indoor space with the bamboo forest landscape.
  2. Insulation Treatment: Inner insulation layers need to be set on the walls and roofs, and triple-glazed windows should be selected to enhance heat insulation performance. In extremely cold areas, heat pump auxiliary heating technology can be added; in humid environments, vapor barriers and ventilation designs (such as exhaust fans and high windows) need to be well implemented to prevent internal condensation.

V. Compliance and Post-maintenance

  1. Approval Procedures: If building on rural homesteads, it is necessary to go through the house-building approval process according to local requirements and provide structural drawings stamped by an engineer. Cultivated land and basic farmland are strictly prohibited from construction, and forest land requires forestry approval. Leased land can mostly only be used as temporary buildings.
  2. Rust Prevention and Corrosion Resistance: During the construction stage, all cutting and welding incisions need to be polished and painted with epoxy primer + topcoat. Check the welds, corners, and other parts every year, and immediately repaint any rust spots found. The repainting cycle should be adjusted according to the environmental humidity (8-12 years in inland dry areas and 3-5 years in coastal areas).
  3. Waterproof Sealing: The sealant around doors and windows, container splicing seams, and roof gutters needs to be replaced every 5-7 years. Clean the roof leaves every year, and strictly prohibit water accumulation to prevent steel plate corrosion.