House Prefabricated Component Installation Tutorial
The house prefabricated component installation tutorial mainly includes the installation processes of single-story prefabricated modular houses, prefabricated composite slabs, prefabricated wall panels, and prefabricated floor slabs and beams, as detailed below:

Single-story prefabricated modular house installation process: According to the design drawings and construction specifications, transport the prefabricated modular house components to the construction site and assemble and connect them in an orderly manner. During installation, ensure that the connections between components are firm and reliable, meeting design requirements, while paying attention to the horizontal and vertical alignment of the components to ensure the overall stability of the house.
Prefabricated composite slab installation process: Before lifting, carefully inspect the appearance quality of the composite slabs to ensure there are no cracks, distortions, or other defects. For lifting composite slabs, a lifting steel beam can be used to ensure that the lifting points bear force simultaneously, allowing the component to be lifted smoothly and avoiding cracks or distortions during the lifting process. The tower crane slowly lifts the prefabricated slab to above the installation position, then slowly lowers and adjusts its position to ensure accurate placement of the composite slab.
Prefabricated wall panel installation process: First, perform positioning by measuring and marking the positioning lines for the exterior wall panels through lifting measurements to ensure the accuracy of the wall panel installation positions. Then, provide support by using a dedicated support system to temporarily fix the wall panels and prevent them from toppling over. Next, make adjustments by correcting skewed reinforcement, using a dedicated reinforcement positioning plate to verify the positioning and vertical alignment of the reserved reinforcement, placing adjustment shims, and using a level to verify the elevation to ensure that the vertical alignment and flatness of the wall panels meet requirements. Finally, perform concrete pouring to firmly connect the wall panels to the structure.
Full prefabricated installation details for the stable connection of prefabricated floor slabs and beams: When installing prefabricated floor slabs, ensure that the connection areas with the beams are clean and free of debris. According to design requirements, use dedicated connectors or welding methods to firmly connect the floor slabs and beams, ensuring the strength and stability of the connection areas. During installation, pay attention to the horizontal and vertical alignment of the floor slabs to ensure the overall structural safety and reliability of the house.