How to Install Double-Unit Mobile Toilets
Admin October 12, 2026
The installation of double-unit mobile toilets requires selecting the appropriate method based on the structural design. The installation steps for common double-connected and double-squat (non-connected) structures are as follows:

I. Installation Process for Double-Connected Mobile Toilets
Foundation Preparation
- Geological Survey: Evaluate the soil's load-bearing capacity and drainage conditions to ensure foundation stability.
- Concrete Foundation Slab: Use a concrete slab with a flatness error of ≤5mm as the support platform. Pre-embed sewage pipe interfaces (with a pipe diameter increased by approximately 30% compared to single-unit toilets) and reserve installation pits for septic tanks.
- Positioning of Pre-embedded Parts: Mark the lifting points, pipe interfaces, and ventilation system locations according to the design drawings to ensure subsequent alignment accuracy.
Main Body Lifting
- Selection of Lifting Equipment: Choose a crane with an appropriate tonnage based on the weight of the toilet unit (usually 2-5 tons). The lifting points must undergo load-bearing calculations (generally arranged on structural beams).
- Installation of Sealing Strips: Before lifting, check the integrity of the sealing strips between the base and the foundation to avoid leakage risks.
- Horizontal Calibration: Use a laser level to adjust the angle of the toilet unit to ensure complete alignment with the foundation slab.
Pipe Connection
- Water Inlet System: Install dual independent valves to control the water supply to each toilet compartment separately, facilitating isolation operations during maintenance.
- Sewage System: Use inclined tee connectors (with an inclination angle of 15°-20°) to converge the sewage pipes. The slope of the main pipe must be ≥2% to ensure smooth drainage.
Equipment Debugging
- Flush Valve: Adjust the water pressure to 0.2-0.3MPa to ensure that the water-saving flush valve uses ≤4L of water per flush.
- Ventilation System: Test the total air volume (≥80m³/h) and balance the exhaust pressure in each toilet compartment by adjusting the branch air valves.
Installation of External Facilities
- Lighting System: Use IP65-rated waterproof fixtures. The power supply lines should pass through waterproof sleeves, and sealant should be applied at the interfaces.
- Warning Lights: Install them at the four corners of the toilet roof, with a height of ≥2.5m, to ensure 360° visibility.
II. Installation Process for Double-Squat Mobile Toilets (Non-Connected)
- Base Assembly: Place the back panel, align it with the sewage hole, and secure it. Install the side and front panels and tighten the slots.
- Frame Installation: Install the ventilation louvers and top structure. Use a pneumatic nail gun to drive in fixing nails (with a spacing of ≤15cm).
- Overall Erection: Two people collaborate to lift the toilet body, adjust it to a vertical position, and then secure the base to the ground connectors.
Precautions: Before installation, verify the design drawings against the site conditions. All pipe connections must undergo anti-seepage treatment. During the debugging phase, simulate usage scenarios to verify system stability.