Construction Methods for Concrete Prefabricated House Roofs
Admin September 18, 2026
The construction methods for concrete prefabricated house roofs mainly include two parts: construction preparation and construction techniques.

I. Construction Preparation
- Material Selection: For cement-based materials, P.O 42.5 ordinary Portland cement is selected, with medium sand as fine aggregate and 5-10mm crushed stone as coarse aggregate. Municipal tap water is used for mixing. Among functional materials, extruded polystyrene board (XPS) is used for the insulation layer, 4mm thick SBS modified bitumen waterproof membrane for the waterproof layer, and polyurethane building sealant for sealing. Auxiliary materials include interface treatment agents, isolation layers, and steel mesh sheets.
- Equipment Configuration: Equipment such as forced-action mortar mixers, concrete delivery pumps, electric trowels, membrane laying machines, laser line projectors, and needle-type thickness gauges are required to ensure construction accuracy and efficiency.
- Installation of Prefabricated Roof Panels: After installation, the panel joints are filled with C30 micro-expanding fine aggregate concrete to a depth of at least half the panel thickness. After 7 days of curing, the bearing capacity is tested, and the panel deflection should be ≤ L/200 (where L is the panel span). For the acceptance of the roof structural layer, the surface flatness error should be ≤ 5mm/2m, with internal and external corners rounded to R=50mm. The areas around pipe roots and embedded parts should be tightly filled with expanding fireproof sealant. Before construction, a 'Special Construction Plan for Roof Engineering' should be prepared, and three-level technical disclosures (project chief engineer → construction worker → operation team) should be completed to clarify key process operation points, quality acceptance standards, and emergency measures.
II. Construction Techniques
- Process Flow: Structural layer acceptance → measurement and layout → pipe root sealing → base layer cleaning → watering for moisture → setting up mortar reference points → laying mortar → vibrating and compacting → surface finishing → curing → dividing joint treatment.
- Key Operation Points:
- Measurement and Layout: Set up mortar reference points (50×50mm in size, spaced 1.5m×1.5m apart) according to a 2% drainage slope, directing the drainage towards the gutter outlet. The slope around the gutter outlet should be increased to 5% within a 500mm radius.
- Pipe Root Treatment: For pipes protruding from the roof (with a diameter ≤ 100mm), chisel out a 20mm deep circular groove at the root, apply a 2mm thick interface treatment agent, and pour C25 fine aggregate concrete (mixed with 5% expanding agent) to the height of the pipe root and finish the surface.
- Roof Construction Sequence: Either the conventional method (insulation first, then waterproofing) or the inverted method (waterproofing first, then insulation) can be used. For self-built houses, insulation can be achieved through internal structural insulation or elevated thermal insulation (by building 10-20cm brick piers and then installing prefabricated panels, followed by plastering with finishing mortar). The waterproof layer can be either rigid (waterproof mortar or fine aggregate concrete) or flexible (membrane waterproofing).
- Standard Six-Step Method: Base layer cleaning → overall application of waterproof coating (with special attention to pipe openings and corners) → node reinforcement (using the 'one fabric, three coats' technique) → full laying of polyester fabric → final coating application + closed water test (water storage ≥ 10cm, no leakage for 24-48 hours) → pouring a 2cm cement mortar protective layer and planning the drainage slope.